Documents
BOP After Action Report on 2019 Freezing Conditions at MDC Federal Jail
July 1, 2021
Exhibit 1
After Action Report
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 1 of 31 PageID #: 1434
Exhibit 1
After Action Report
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 1 of 31 PageID #: 1434
After Action Report
Partial Electrical and Reported Heating Outage
Civil Disturbance
Metropolitan Detention Center
Brooklyn, New York
Submitted by: J. Ray Ormond, Regional Director
BOP AFTER ACTION REPORT 001
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 2 of 31 PageID #: 1435
After Action Report
Partial Electrical and Reported Heating Outage
Civil Disturbance
Metropolitan Detention Center
Brooklyn, New York
Submitted by: J. Ray Ormond, Regional Director
BOP AFTER ACTION REPORT 001
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 2 of 31 PageID #: 1435
TABLE OF CONTENTS
Introduction/Executive Summary................................3-5
Chronology of Events.........................................5-16
Analysis of Events..........................................17-28
Conclusions...................................................28
Recommendations............................................28-29
Inmate Information............................................30
Cost/Impact Statement.........................................30
BOP AFTER ACTION REPORT 002
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 3 of 31 PageID #: 1436
TABLE OF CONTENTS
Introduction/Executive Summary................................3-5
Chronology of Events.........................................5-16
Analysis of Events..........................................17-28
Conclusions...................................................28
Recommendations............................................28-29
Inmate Information............................................30
Cost/Impact Statement.........................................30
BOP AFTER ACTION REPORT 002
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 3 of 31 PageID #: 1436
Introduction:
The Metropolitan Detention Center (MDC) in Brooklyn, New York, is
an Administrative Level facility that serves the Eastern and Southern
Districts of New York. The primary mission of the facility is to
house pre-trial inmates awaiting court action for the United States
Marshals Service (USMS).
On February 8, 2019, the Northeast Regional Director appointed an
After Action Review (AAR) Team to review a series of events that
occurred at the MDC between the dates of Sunday, January 27, 2019
to Sunday, February 3, 2019. The review was conducted to analyze
the events that led to mechanical system failures resulting in the
partial loss of electricity and reported loss of heat to the
institution, along with an examination of existing practices and
procedures that contributed to a subsequent Civil Disturbance.
The review team consisted of:
Andre Matevousian, Complex Warden, FCC Florence
Louis Milusnic, Complex Warden, FCC Victorville
Jeffrey Greene, Associate Warden, FDC Seatac
Victor Moreno, Associate Warden, USP Atlanta
Steve Reiser, Associate Warden, FCC Coleman
Darrin Howard, Regional Counsel, Northeast Regional Office
Tovia Knight, Public Affairs Specialist, Central Office
Dr. Te Core Ballom, RADM Medical Director, South Central Region
Marc Wolff, Chief Facilities Programs, Central Office
Neil Morgan, Facilities Manager, FDC Philadelphia
James Gibbs, Correctional Services Specialist, Northeast Region
Michael Drake, Emergency Management Specialist, Central Office
The review was conducted on March 5-8, 2019.
BOP AFTER ACTION REPORT 003
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 4 of 31 PageID #: 1437
Introduction:
The Metropolitan Detention Center (MDC) in Brooklyn, New York, is
an Administrative Level facility that serves the Eastern and Southern
Districts of New York. The primary mission of the facility is to
house pre-trial inmates awaiting court action for the United States
Marshals Service (USMS).
On February 8, 2019, the Northeast Regional Director appointed an
After Action Review (AAR) Team to review a series of events that
occurred at the MDC between the dates of Sunday, January 27, 2019
to Sunday, February 3, 2019. The review was conducted to analyze
the events that led to mechanical system failures resulting in the
partial loss of electricity and reported loss of heat to the
institution, along with an examination of existing practices and
procedures that contributed to a subsequent Civil Disturbance.
The review team consisted of:
Andre Matevousian, Complex Warden, FCC Florence
Louis Milusnic, Complex Warden, FCC Victorville
Jeffrey Greene, Associate Warden, FDC Seatac
Victor Moreno, Associate Warden, USP Atlanta
Steve Reiser, Associate Warden, FCC Coleman
Darrin Howard, Regional Counsel, Northeast Regional Office
Tovia Knight, Public Affairs Specialist, Central Office
Dr. Te Core Ballom, RADM Medical Director, South Central Region
Marc Wolff, Chief Facilities Programs, Central Office
Neil Morgan, Facilities Manager, FDC Philadelphia
James Gibbs, Correctional Services Specialist, Northeast Region
Michael Drake, Emergency Management Specialist, Central Office
The review was conducted on March 5-8, 2019.
BOP AFTER ACTION REPORT 003
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 4 of 31 PageID #: 1437
Executive Summary:
On Sunday, January 27, 2019, at 12:50 p.m., a fire alarm was activated
in the second floor mechanical room. An immediate response to the
area revealed a fire that resulted in loss of power to one of the
main priority switches that services approximately sixty-six (66)
electrical panels throughout the West building.
The New York City Fire Department (NYFD), responded to the
institution and extinguished the electrical fire and coordinated
with Con Edison (electrical service provider) to isolate the power
feed to the damaged priority switch. Based on the impact of the fire
and the loss of power that resulted in security concerns, the facility
was placed on lock-down status to assess the damage and make emergency
repairs.
Over the next week, concerns were voiced by inmates and external
stakeholders regarding the reported conditions of confinement at the
MDC. Specifically, the majority of concerns surrounded reports of
limited access to medical care, lack of adequate heat and electricity
in cells, access to legal visits and calls, and a lack of transparency
regarding the status of repairs and current living conditions.
As a result, public concern was voiced to the media, local government
officials, courts, and members of Congress. As part of the review,
the AAR team identified over seven (7) visits from twenty-four (24)
officials to the MDC during the incident period who sought to observe
and inquire into the incident and be briefed on the course of actions
being taken to remedy their concerns. Most notably, the Chief
United States District Judge, Eastern District of New York, ordered
that a representative of the Federal Defenders of New York and the
U.S. Attorney’s Office, Eastern District of New York be permitted
to inspect each housing unit in the West Building and speak directly
with inmates on February 1, 2019. Additionally, U.S. Congressional
members toured the facility on Friday (2/1), Saturday (2/2), Sunday
(2/3), and Monday, (2/11).
During the course of the week, the institution operated on a variety
of schedules, from modified operations to full lock down procedures.
As a result, normal services the MDC provides to the inmate
population, courts, and the public were suspended or delayed.
Based on community concerns regarding reported living conditions,
a large gathering of protestors converged on the MDC for several days.
BOP AFTER ACTION REPORT 004
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 5 of 31 PageID #: 1438
Executive Summary:
On Sunday, January 27, 2019, at 12:50 p.m., a fire alarm was activated
in the second floor mechanical room. An immediate response to the
area revealed a fire that resulted in loss of power to one of the
main priority switches that services approximately sixty-six (66)
electrical panels throughout the West building.
The New York City Fire Department (NYFD), responded to the
institution and extinguished the electrical fire and coordinated
with Con Edison (electrical service provider) to isolate the power
feed to the damaged priority switch. Based on the impact of the fire
and the loss of power that resulted in security concerns, the facility
was placed on lock-down status to assess the damage and make emergency
repairs.
Over the next week, concerns were voiced by inmates and external
stakeholders regarding the reported conditions of confinement at the
MDC. Specifically, the majority of concerns surrounded reports of
limited access to medical care, lack of adequate heat and electricity
in cells, access to legal visits and calls, and a lack of transparency
regarding the status of repairs and current living conditions.
As a result, public concern was voiced to the media, local government
officials, courts, and members of Congress. As part of the review,
the AAR team identified over seven (7) visits from twenty-four (24)
officials to the MDC during the incident period who sought to observe
and inquire into the incident and be briefed on the course of actions
being taken to remedy their concerns. Most notably, the Chief
United States District Judge, Eastern District of New York, ordered
that a representative of the Federal Defenders of New York and the
U.S. Attorney’s Office, Eastern District of New York be permitted
to inspect each housing unit in the West Building and speak directly
with inmates on February 1, 2019. Additionally, U.S. Congressional
members toured the facility on Friday (2/1), Saturday (2/2), Sunday
(2/3), and Monday, (2/11).
During the course of the week, the institution operated on a variety
of schedules, from modified operations to full lock down procedures.
As a result, normal services the MDC provides to the inmate
population, courts, and the public were suspended or delayed.
Based on community concerns regarding reported living conditions,
a large gathering of protestors converged on the MDC for several days.
BOP AFTER ACTION REPORT 004
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 5 of 31 PageID #: 1438
On Sunday, February 3, 2019, the large gathering of approximately
50 to 60 protesters (based on video footage)entered the main lobby
of the MDC and engaged in a physical confrontation with staff. After
attempts to contain the protestors and after being pushed back into
the lobby by protestors, employees utilized physical force to remove
the protestors from the institution. During the confrontation,
staff deploy chemical agents in an effort to limit injury to both
staff and protestors, and to remove the protestors from inside the
institution’s main lobby. This action proved effective and staff
were able to remove all individuals from the institution without
further incident.
On Sunday, February 3, 2019, at approximately 6:30 p.m., emergency
repairs were finalized on the priority switch gear that was destroyed
in the fire and power was fully restored to all areas of the
institution.
Chronology of Events:
Friday, January 4, 2019
6:30 a.m.: The West building sustains power loss and the Facilities
Department staff activated the generators without delay. The
uninterrupted power supply (UPS) system immediately activated
emergency lighting throughout the affected areas, which included
unit common area lights. An examination of the core problem is
isolated to a breaker impacting priority switch gear #3
Saturday, January 5, 2019
1:30 a.m.: An outside electrical contractor is called into the
facility to examine the electrical power issues with switch gear #3.
During this time, all three (3) generators fail and no longer start,
resulting in no back-up power to the facility. At this time, the
institution has power to all areas with the exception of inmate cells,
phones and computers, and food services.
5:00 p.m.: The electrical contractor is successful in reestablishing
power to switch gear #3 and utility power is restored to the affected
areas described in the 1/5/19 1:30 a.m. outage. The contractor
report indicates he checked the breaker, verified all connections
BOP AFTER ACTION REPORT 005
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 6 of 31 PageID #: 1439
On Sunday, February 3, 2019, the large gathering of approximately
50 to 60 protesters (based on video footage)entered the main lobby
of the MDC and engaged in a physical confrontation with staff. After
attempts to contain the protestors and after being pushed back into
the lobby by protestors, employees utilized physical force to remove
the protestors from the institution. During the confrontation,
staff deploy chemical agents in an effort to limit injury to both
staff and protestors, and to remove the protestors from inside the
institution’s main lobby. This action proved effective and staff
were able to remove all individuals from the institution without
further incident.
On Sunday, February 3, 2019, at approximately 6:30 p.m., emergency
repairs were finalized on the priority switch gear that was destroyed
in the fire and power was fully restored to all areas of the
institution.
Chronology of Events:
Friday, January 4, 2019
6:30 a.m.: The West building sustains power loss and the Facilities
Department staff activated the generators without delay. The
uninterrupted power supply (UPS) system immediately activated
emergency lighting throughout the affected areas, which included
unit common area lights. An examination of the core problem is
isolated to a breaker impacting priority switch gear #3
Saturday, January 5, 2019
1:30 a.m.: An outside electrical contractor is called into the
facility to examine the electrical power issues with switch gear #3.
During this time, all three (3) generators fail and no longer start,
resulting in no back-up power to the facility. At this time, the
institution has power to all areas with the exception of inmate cells,
phones and computers, and food services.
5:00 p.m.: The electrical contractor is successful in reestablishing
power to switch gear #3 and utility power is restored to the affected
areas described in the 1/5/19 1:30 a.m. outage. The contractor
report indicates he checked the breaker, verified all connections
BOP AFTER ACTION REPORT 005
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 6 of 31 PageID #: 1439
were made within the gear, no bus or wires were shorted, all
connections within the gear were installed and secured, and none of
the stabs (generator breaker connection point) had anything loose
within the gear. The breaker was reinstalled. However, all three
generators are still inoperable and institution staff work with a
local generator contractor to install an emergency generator. The
institution rented a generator on January 5, 2019, and it was returned
January 17, 2019. The institution returned to normal operations at
5:35 p.m.
Monday, January 7, 2019
7:00 a.m.: Electrical and generator contractors arrive at MDC to
install temporary lines and continue to troubleshoot institution
generators.
Tuesday, January 8, 2019
10:30 a.m.: Temporary generator installed and connected to second
floor electrical room.
Thursday, January 10, 2019
1:30 p.m.: Generator contractor repairs all three institution
generators by replacing the diodes, which are essentially, fuses.
Monday, January 21, 2019
During the early morning hours, after outside temperatures drop to
3 degrees, multiple heating coils in the HVAC system freeze and burst,
resulting in loss of heat to eight (8) of the fifteen (15) main systems
in the West building. These areas and dates of repairs are noted
below.
1. AHU 4-1 (Unit G43 Common Areas) – Repaired 1/22/19
2. AHU 4-6 (Unit G42 Cells) – Repaired 1/22/19
3. AHU 6-6 (Unit I62 Cells) – Repaired 1/22/19
4. AHU 7-3 (Unit J72 Common Areas) – Repaired 1/23/19
5. AHU P-1 (SHU Range 3) – Repaired 1/22/19
6. AHU P-3 (SHU Office Areas / Unit Team Offices floors 4-9)
Repaired 1/23/2019. Staff provided alternative work areas.
BOP AFTER ACTION REPORT 006
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 7 of 31 PageID #: 1440
were made within the gear, no bus or wires were shorted, all
connections within the gear were installed and secured, and none of
the stabs (generator breaker connection point) had anything loose
within the gear. The breaker was reinstalled. However, all three
generators are still inoperable and institution staff work with a
local generator contractor to install an emergency generator. The
institution rented a generator on January 5, 2019, and it was returned
January 17, 2019. The institution returned to normal operations at
5:35 p.m.
Monday, January 7, 2019
7:00 a.m.: Electrical and generator contractors arrive at MDC to
install temporary lines and continue to troubleshoot institution
generators.
Tuesday, January 8, 2019
10:30 a.m.: Temporary generator installed and connected to second
floor electrical room.
Thursday, January 10, 2019
1:30 p.m.: Generator contractor repairs all three institution
generators by replacing the diodes, which are essentially, fuses.
Monday, January 21, 2019
During the early morning hours, after outside temperatures drop to
3 degrees, multiple heating coils in the HVAC system freeze and burst,
resulting in loss of heat to eight (8) of the fifteen (15) main systems
in the West building. These areas and dates of repairs are noted
below.
1. AHU 4-1 (Unit G43 Common Areas) – Repaired 1/22/19
2. AHU 4-6 (Unit G42 Cells) – Repaired 1/22/19
3. AHU 6-6 (Unit I62 Cells) – Repaired 1/22/19
4. AHU 7-3 (Unit J72 Common Areas) – Repaired 1/23/19
5. AHU P-1 (SHU Range 3) – Repaired 1/22/19
6. AHU P-3 (SHU Office Areas / Unit Team Offices floors 4-9)
Repaired 1/23/2019. Staff provided alternative work areas.
BOP AFTER ACTION REPORT 006
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 7 of 31 PageID #: 1440
7. AHU 2-9 (Medical Department) – Repaired 1/22/19
8. AHU 3-2 (Food Services) – Repaired 1/22/2019
6:00 a.m.: Power to priority switchgear #3 fails, resulting in loss
of power to multiple areas in the West building, to include inmate
cells, phones and computers, and food services. Con Edison Command
Center contacted and reported two feeder cables inoperative. Con
Edison dispatches staff to MDC.
8:00 a.m.: Con Edison arrives at the MDC to assess the loss of power
and discovers a malfunctioning 5000 amp fuse located in the utility
providers high voltage network room of the West building. MDC staff
do not have access to the utility provider’s room as it is owned and
restricted by the utility company.
2:00 p.m.: Repairs are finalized by Con Edison and power is restored.
Tuesday, January 22, 2019
4:25 p.m.: Warden reports to Regional Director heat restored to
Special Housing, Food Services, Education, Health Services, Unit 52,
Unit 72. Staff continue working on Unit 62. Part has been ordered
for Unit Team Staff work areas.
8:13 p.m.: Warden reports to Regional Director Facilities Department
Staff have been working on heating coils entire day and will continue
repairs next day. Additional blankets have been provided in all
affected units.
Wednesday, January 23, 2019
2:55 p.m.: Temperature readings in all units range between 64 and
78, with the exception of Unit 62. Staff working on Unit 62 heating
coil and provided inmates with additional linens.
6:12 p.m.: Warden reports to Regional Director heat restored to Unit
Team Staff work areas.
BOP AFTER ACTION REPORT 007
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 8 of 31 PageID #: 1441
7. AHU 2-9 (Medical Department) – Repaired 1/22/19
8. AHU 3-2 (Food Services) – Repaired 1/22/2019
6:00 a.m.: Power to priority switchgear #3 fails, resulting in loss
of power to multiple areas in the West building, to include inmate
cells, phones and computers, and food services. Con Edison Command
Center contacted and reported two feeder cables inoperative. Con
Edison dispatches staff to MDC.
8:00 a.m.: Con Edison arrives at the MDC to assess the loss of power
and discovers a malfunctioning 5000 amp fuse located in the utility
providers high voltage network room of the West building. MDC staff
do not have access to the utility provider’s room as it is owned and
restricted by the utility company.
2:00 p.m.: Repairs are finalized by Con Edison and power is restored.
Tuesday, January 22, 2019
4:25 p.m.: Warden reports to Regional Director heat restored to
Special Housing, Food Services, Education, Health Services, Unit 52,
Unit 72. Staff continue working on Unit 62. Part has been ordered
for Unit Team Staff work areas.
8:13 p.m.: Warden reports to Regional Director Facilities Department
Staff have been working on heating coils entire day and will continue
repairs next day. Additional blankets have been provided in all
affected units.
Wednesday, January 23, 2019
2:55 p.m.: Temperature readings in all units range between 64 and
78, with the exception of Unit 62. Staff working on Unit 62 heating
coil and provided inmates with additional linens.
6:12 p.m.: Warden reports to Regional Director heat restored to Unit
Team Staff work areas.
BOP AFTER ACTION REPORT 007
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 8 of 31 PageID #: 1441
Thursday, January 24, 2019
4:30 p.m.: Warden reports to Regional Director he walked the
institution with Local Union President and measured temperatures in
each area, which reflected temperatures between 63 and 74 degrees.
Sunday, January 27, 2019
12:50 p.m.: Fire alarm activates in second floor mechanical room.
12:51 p.m.: Institution placed on lock down status and NYFD
dispatches to MDC. Visiting room evacuated.
12:57 p.m.: NYFD arrives to MDC.
1:53 p.m.: NYFD fully extinguishes fire and renders building safe.
2:00 p.m.: NYFD Fire Marshal and utility provider Con Edison conduct
fire inspection.
2:21 p.m.: NYFD exits building.
2:42 p.m.: NYFD exits property.
4:30 p.m.: Facilities staff replace smoke detector in second floor
mechanical room and begin assessing damage to priority switch
gear #3. Staff begin to establish emergency lighting throughout the
facility.
5:02 p.m.: Warden provides synopsis to Regional Director of day’s
activities. Warden indicated: 1) No staff or inmate injuries, 2)
East Building (female inmate housing) is unaffected, 3) Power
unavailable in staff offices, inmate cells, food services, receiving
and discharge area, and visiting. Computers are not operational.
4) Power outage did not impact cameras, housing unit common area
lighting, institution heat, or elevator operations. 5) Institution
will remain secured (lock down) and inmates will receive evening
meals in assigned cells, 6) Medical staff are conducting pill line
in each unit and going to each cell to address inmate concerns,
7) Visiting has been cancelled, Con Edison was on site today to
evaluate outage and will return 1/28/19 to bypass damaged switch
gear.
BOP AFTER ACTION REPORT 008
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 9 of 31 PageID #: 1442
Thursday, January 24, 2019
4:30 p.m.: Warden reports to Regional Director he walked the
institution with Local Union President and measured temperatures in
each area, which reflected temperatures between 63 and 74 degrees.
Sunday, January 27, 2019
12:50 p.m.: Fire alarm activates in second floor mechanical room.
12:51 p.m.: Institution placed on lock down status and NYFD
dispatches to MDC. Visiting room evacuated.
12:57 p.m.: NYFD arrives to MDC.
1:53 p.m.: NYFD fully extinguishes fire and renders building safe.
2:00 p.m.: NYFD Fire Marshal and utility provider Con Edison conduct
fire inspection.
2:21 p.m.: NYFD exits building.
2:42 p.m.: NYFD exits property.
4:30 p.m.: Facilities staff replace smoke detector in second floor
mechanical room and begin assessing damage to priority switch
gear #3. Staff begin to establish emergency lighting throughout the
facility.
5:02 p.m.: Warden provides synopsis to Regional Director of day’s
activities. Warden indicated: 1) No staff or inmate injuries, 2)
East Building (female inmate housing) is unaffected, 3) Power
unavailable in staff offices, inmate cells, food services, receiving
and discharge area, and visiting. Computers are not operational.
4) Power outage did not impact cameras, housing unit common area
lighting, institution heat, or elevator operations. 5) Institution
will remain secured (lock down) and inmates will receive evening
meals in assigned cells, 6) Medical staff are conducting pill line
in each unit and going to each cell to address inmate concerns,
7) Visiting has been cancelled, Con Edison was on site today to
evaluate outage and will return 1/28/19 to bypass damaged switch
gear.
BOP AFTER ACTION REPORT 008
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 9 of 31 PageID #: 1442
Monday, January 28, 2019
8:00 a.m. – Con Edison arrives on site to confirm power has been
isolated to priority switch gear #3 and discovers following an
inspection, severe damage to the electrical cabinet and three (3)
bad 5000 amp fuses. Due to fire damage, institution generator and
portable generator cannot provide service to priority switch gear
#3 until bypass electrical panel is installed.
1:00 p.m. – Electrical contractor arrives to assess and evaluate
replacement of priority switch gear #3 cabinet. The contractor was
contacted January 27, 2019, but could not begin work until the area
was determined safe, on January 28, 2019, by the utility provider.
5:04 p.m.: Warden provides synopsis of day’s activities. Warden
indicated: 1) the January 4, 2019, and January 27, 2019, power
interruptions were on the same switch gear #3, but were not in the
same area and the January 27, 2019 fire did not damage the January
4, 2019, reinstalled breaker. 2) Temporary lighting was placed in
food services for preparation of hot meals, lighting and computers
are working in health services, temporary lighting placed in
receiving and discharge area for processing of inmates. 3) Inmates
have been out of their cells since lunch, with access to unit common
areas, outdoor recreation, showers, and hot water dispensers. 4)
Currently, no lighting in the visiting room and visits remain
suspended. 5) A second staff member was added to each housing unit,
and units will be secured at 8:00 p.m. 6) Electrical contractor was
at the institution all day testing impacted areas for needed repairs.
Tuesday, January 29, 2019
9:55 a.m.: Housing Units return to normal operation, allowing inmates
access to unit common areas, showers, outdoor recreation, and hot
water dispensers. Additional staff assigned to each unit to assist
assigned Officer. Visitation remains cancelled due to no lighting
in Visiting Room.
Structural engineering firm Miller-Remick arrives to MDC to conduct
assessment of electrical fire and damage. Purpose of the visit is
to provide design recommendations to replace damaged switch gear and
make recommendations to prevent similar events in the future.
BOP AFTER ACTION REPORT 009
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 10 of 31 PageID #: 1443
Monday, January 28, 2019
8:00 a.m. – Con Edison arrives on site to confirm power has been
isolated to priority switch gear #3 and discovers following an
inspection, severe damage to the electrical cabinet and three (3)
bad 5000 amp fuses. Due to fire damage, institution generator and
portable generator cannot provide service to priority switch gear
#3 until bypass electrical panel is installed.
1:00 p.m. – Electrical contractor arrives to assess and evaluate
replacement of priority switch gear #3 cabinet. The contractor was
contacted January 27, 2019, but could not begin work until the area
was determined safe, on January 28, 2019, by the utility provider.
5:04 p.m.: Warden provides synopsis of day’s activities. Warden
indicated: 1) the January 4, 2019, and January 27, 2019, power
interruptions were on the same switch gear #3, but were not in the
same area and the January 27, 2019 fire did not damage the January
4, 2019, reinstalled breaker. 2) Temporary lighting was placed in
food services for preparation of hot meals, lighting and computers
are working in health services, temporary lighting placed in
receiving and discharge area for processing of inmates. 3) Inmates
have been out of their cells since lunch, with access to unit common
areas, outdoor recreation, showers, and hot water dispensers. 4)
Currently, no lighting in the visiting room and visits remain
suspended. 5) A second staff member was added to each housing unit,
and units will be secured at 8:00 p.m. 6) Electrical contractor was
at the institution all day testing impacted areas for needed repairs.
Tuesday, January 29, 2019
9:55 a.m.: Housing Units return to normal operation, allowing inmates
access to unit common areas, showers, outdoor recreation, and hot
water dispensers. Additional staff assigned to each unit to assist
assigned Officer. Visitation remains cancelled due to no lighting
in Visiting Room.
Structural engineering firm Miller-Remick arrives to MDC to conduct
assessment of electrical fire and damage. Purpose of the visit is
to provide design recommendations to replace damaged switch gear and
make recommendations to prevent similar events in the future.
BOP AFTER ACTION REPORT 009
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 10 of 31 PageID #: 1443
Wednesday, January 30, 2019
Housing Units remain in normal operation, allowing inmates access
to unit common areas, showers, outdoor recreation, and hot water
dispensers. Additional staff assigned to each unit to assist
assigned Officer. Visitation remains cancelled due to no lighting
in Visiting Room.
9:27 a.m.: Institution receives Miller-Remick Engineering Field
Report. Report indicates more test are planned before attempting
to re-energize emergency feeds, and provides phases of work that will
continue for restoring power.
Contractor continues work on installation of new temporary main
disconnect and removal of damaged wires from switchgear cabinet for
connection of new equipment.
Thursday, January 31, 2019
Housing Units remain in normal operation, allowing inmates access
to unit common areas, showers, outdoor recreation, and hot water
dispensers. Additional staff assigned to each unit to assist
assigned Officer. Visitation remains cancelled due to no lighting
in Visiting Room.
3:50 p.m.: Warden reports to Regional Director all units temperatures
are between 66 and 75, with the exception of one unit (53.4).
Adjustments were made to the air handler of this one unit. Outside
temperatures on January 31, 2019, range between 2 and 17.
Electrical contractor submits work ticket to Con Edison to schedule
power restoration. Contractor continues work on installation of new
temporary main disconnect and removal of damaged wires from
switchgear cabinet for connection of new equipment.
Friday, February 1, 2019
Housing Units remain in normal operation, allowing inmates access
to unit common areas, showers, outdoor recreation, and hot water
dispensers. Additional staff assigned to each unit to assist
assigned Officer. Visitation remains cancelled due to no lighting
in Visiting Room.
BOP AFTER ACTION REPORT 010
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 11 of 31 PageID #: 1444
Wednesday, January 30, 2019
Housing Units remain in normal operation, allowing inmates access
to unit common areas, showers, outdoor recreation, and hot water
dispensers. Additional staff assigned to each unit to assist
assigned Officer. Visitation remains cancelled due to no lighting
in Visiting Room.
9:27 a.m.: Institution receives Miller-Remick Engineering Field
Report. Report indicates more test are planned before attempting
to re-energize emergency feeds, and provides phases of work that will
continue for restoring power.
Contractor continues work on installation of new temporary main
disconnect and removal of damaged wires from switchgear cabinet for
connection of new equipment.
Thursday, January 31, 2019
Housing Units remain in normal operation, allowing inmates access
to unit common areas, showers, outdoor recreation, and hot water
dispensers. Additional staff assigned to each unit to assist
assigned Officer. Visitation remains cancelled due to no lighting
in Visiting Room.
3:50 p.m.: Warden reports to Regional Director all units temperatures
are between 66 and 75, with the exception of one unit (53.4).
Adjustments were made to the air handler of this one unit. Outside
temperatures on January 31, 2019, range between 2 and 17.
Electrical contractor submits work ticket to Con Edison to schedule
power restoration. Contractor continues work on installation of new
temporary main disconnect and removal of damaged wires from
switchgear cabinet for connection of new equipment.
Friday, February 1, 2019
Housing Units remain in normal operation, allowing inmates access
to unit common areas, showers, outdoor recreation, and hot water
dispensers. Additional staff assigned to each unit to assist
assigned Officer. Visitation remains cancelled due to no lighting
in Visiting Room.
BOP AFTER ACTION REPORT 010
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 11 of 31 PageID #: 1444
6:00 a.m.: Temperature readings in all units range between 63.8 and
74. Outside temperatures on February 1, 2019, range between 10 and
22.
9:35 a.m.: Staff call for assistance; inmates refuse to return to
assigned cells.
12:00 p.m.: Elevators become inoperable and inmates returned to
their assigned cells. Some inmates become disruptive and refuse;
others become disruptive inside cells, kicking doors, covering
windows, setting fire.
1:30 p.m. Bureau of Prisons becomes aware of New York Times article,
titled “No Heat for Days at Jail in Brooklyn Where Hundreds of Inmates
Are Sick and ‘Frantic’”.
2:10 p.m.: Staff call for assistance; inmate becomes disruptive while
being escorted by staff.
3:00 p.m.: Temperature readings in all units range between 66 and
74. Outside temperatures on February 1, 2019, range between 10 and
22.
3:45 p.m.: Visit by Thomas E. Mixon, Assistant District Executive,
United States District Court, Southern District of New York. Warden
reports to Regional Director they toured three floors of units,
inspected the temperatures, appeared to be satisfied with the
temperatures, and asked to see the kitchen, at which time he viewed
hot meals being prepared.
4:10 p.m.: Visit by Nydia Velazquez, U.S. Representative, New York
12th District; Dan Wiley, Director for Representative Velazquez;
Melissa Ortiz, Community Relations Director, for Representative
Velazquez. Warden reports to Regional Director they toured eight
units and Special Housing Unit. Appeared satisfied with unit
temperatures but concerned with temperatures in sally port area of
each floor (no staff or inmates assigned) and front lobby of building.
Inspected the water temperature of showers on each floor visited and
appeared satisfied with the results.
4:10 p.m.: Visit by John Ross, Senior Investigator, U.S. Attorney’s
Office; Deirdre Von Dornum, Attorney-in-Charge, Federal Public
Defenders Office, Eastern District of New York. Warden reports
inmates told Ms. Von Dornum they were not receiving medication, told
BOP AFTER ACTION REPORT 011
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 12 of 31 PageID #: 1445
6:00 a.m.: Temperature readings in all units range between 63.8 and
74. Outside temperatures on February 1, 2019, range between 10 and
22.
9:35 a.m.: Staff call for assistance; inmates refuse to return to
assigned cells.
12:00 p.m.: Elevators become inoperable and inmates returned to
their assigned cells. Some inmates become disruptive and refuse;
others become disruptive inside cells, kicking doors, covering
windows, setting fire.
1:30 p.m. Bureau of Prisons becomes aware of New York Times article,
titled “No Heat for Days at Jail in Brooklyn Where Hundreds of Inmates
Are Sick and ‘Frantic’”.
2:10 p.m.: Staff call for assistance; inmate becomes disruptive while
being escorted by staff.
3:00 p.m.: Temperature readings in all units range between 66 and
74. Outside temperatures on February 1, 2019, range between 10 and
22.
3:45 p.m.: Visit by Thomas E. Mixon, Assistant District Executive,
United States District Court, Southern District of New York. Warden
reports to Regional Director they toured three floors of units,
inspected the temperatures, appeared to be satisfied with the
temperatures, and asked to see the kitchen, at which time he viewed
hot meals being prepared.
4:10 p.m.: Visit by Nydia Velazquez, U.S. Representative, New York
12th District; Dan Wiley, Director for Representative Velazquez;
Melissa Ortiz, Community Relations Director, for Representative
Velazquez. Warden reports to Regional Director they toured eight
units and Special Housing Unit. Appeared satisfied with unit
temperatures but concerned with temperatures in sally port area of
each floor (no staff or inmates assigned) and front lobby of building.
Inspected the water temperature of showers on each floor visited and
appeared satisfied with the results.
4:10 p.m.: Visit by John Ross, Senior Investigator, U.S. Attorney’s
Office; Deirdre Von Dornum, Attorney-in-Charge, Federal Public
Defenders Office, Eastern District of New York. Warden reports
inmates told Ms. Von Dornum they were not receiving medication, told
BOP AFTER ACTION REPORT 011
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 12 of 31 PageID #: 1445
her they were locked in cells all week. Inmate in SHU told Ms. Von
Dornum he was freezing, but was not wearing a shirt. Ms. Von Dornum
reported she would be writing to the Court that evening.
4:47 p.m.: Warden reports to Regional Director electrical contractor
continues to work on installation of new electrical panel.
5:56 p.m.: Staff call for assistance; inmate assault on staff.
Multiple groups of activist post notices of planned protest at MDC
on February 2, 2019, at 12:00 p.m., titled “Until There is Heat” and
“Occupy For Humanity”. Unit temperatures are ranging between 66 and
74.
Saturday, February 2, 2019
12:00 a.m.: Inmates cover cell windows, preventing staff from
conducting official count and ensuring the health of the cells
occupants. One employee was injured while removing the inmates from
their cell.
8:40 a.m.: New York Police Department (NYPD) notified institution
regarding anticipated protest at MDC.
9:00 a.m.: Institution placed on lock down status as a result of
inmate activities on February 1, 2019 and February 2, 2019, and
anticipated protest at the MDC.
10:00 a.m.: Groups of protestors arrive outside institution and
inmates begin covering cell door windows and pounding on outer
windows.
11:00 a.m.: The size of the protest group increases and staff report
protesters are inciting inappropriate behavior by inmates.
11:55 a.m.: MDC Brooklyn Disturbance Control Team (DCT) activated.
12:00 p.m.: Temperature readings in all units range between 65 and
80.
1:04 p.m.: Protesters attempt to breach the West Lobby, emergency
response staff block egress and contain individuals from accessing
the building.
BOP AFTER ACTION REPORT 012
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 13 of 31 PageID #: 1446
her they were locked in cells all week. Inmate in SHU told Ms. Von
Dornum he was freezing, but was not wearing a shirt. Ms. Von Dornum
reported she would be writing to the Court that evening.
4:47 p.m.: Warden reports to Regional Director electrical contractor
continues to work on installation of new electrical panel.
5:56 p.m.: Staff call for assistance; inmate assault on staff.
Multiple groups of activist post notices of planned protest at MDC
on February 2, 2019, at 12:00 p.m., titled “Until There is Heat” and
“Occupy For Humanity”. Unit temperatures are ranging between 66 and
74.
Saturday, February 2, 2019
12:00 a.m.: Inmates cover cell windows, preventing staff from
conducting official count and ensuring the health of the cells
occupants. One employee was injured while removing the inmates from
their cell.
8:40 a.m.: New York Police Department (NYPD) notified institution
regarding anticipated protest at MDC.
9:00 a.m.: Institution placed on lock down status as a result of
inmate activities on February 1, 2019 and February 2, 2019, and
anticipated protest at the MDC.
10:00 a.m.: Groups of protestors arrive outside institution and
inmates begin covering cell door windows and pounding on outer
windows.
11:00 a.m.: The size of the protest group increases and staff report
protesters are inciting inappropriate behavior by inmates.
11:55 a.m.: MDC Brooklyn Disturbance Control Team (DCT) activated.
12:00 p.m.: Temperature readings in all units range between 65 and
80.
1:04 p.m.: Protesters attempt to breach the West Lobby, emergency
response staff block egress and contain individuals from accessing
the building.
BOP AFTER ACTION REPORT 012
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 13 of 31 PageID #: 1446
1:20 p.m.: Staff begin institution tours:
Jerrold Nadler, U.S. Representative, New York 10th District;
Robert Gottheim, Director of Relations for Representative Nadler.
Antonio Delgado, U.S. Representative, New York 19th District
Hakeem Jefferies, U.S. Representative, New York 8th District
Nydia Velazquez, U.S. Representative, New York 12th District;
Dan Wiley, Director for Representative Velazquez; Melissa Ortiz,
Community Relations Director, for Representative Velazquez.
Deirdre Von Dornum, Attorney-in-Charge, Federal Public Defenders
Office, Eastern District of New York
Letitia James, Attorney General for the State of New York
Jo Anne Simon, New York State Assembly, 52nd District
Brad Lander, New York City Council, 39th District
Scott Stringer, Comptroller, New York City
Jumaane Williams, Former New York City Council, 45th District
2:30 p.m.: Protesters access the staff parking lot and engage
responding staff in a verbal confrontation. Staff are able to escort
individuals off of government property without further incident.
6:45 p.m.: As staff where preparing to transport an inmate to the
local hospital, protesters blocked the 2nd Avenue gate to prevent an
ambulance from entering the institution. Emergency response staff
were able to move the protesters back onto the street without further
incident.
Contractor continues work on installation of new temporary main
disconnect and removal of damaged wires from switchgear cabinet for
connection of new equipment.
Sunday, February 3, 2019
6:00 a.m.: Bureau of Prisons and Contract staff return to institution
to continue electrical service work. This work included installing
temporary service to switchgear #3 and making final electrical
BOP AFTER ACTION REPORT 013
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 14 of 31 PageID #: 1447
1:20 p.m.: Staff begin institution tours:
Jerrold Nadler, U.S. Representative, New York 10th District;
Robert Gottheim, Director of Relations for Representative Nadler.
Antonio Delgado, U.S. Representative, New York 19th District
Hakeem Jefferies, U.S. Representative, New York 8th District
Nydia Velazquez, U.S. Representative, New York 12th District;
Dan Wiley, Director for Representative Velazquez; Melissa Ortiz,
Community Relations Director, for Representative Velazquez.
Deirdre Von Dornum, Attorney-in-Charge, Federal Public Defenders
Office, Eastern District of New York
Letitia James, Attorney General for the State of New York
Jo Anne Simon, New York State Assembly, 52nd District
Brad Lander, New York City Council, 39th District
Scott Stringer, Comptroller, New York City
Jumaane Williams, Former New York City Council, 45th District
2:30 p.m.: Protesters access the staff parking lot and engage
responding staff in a verbal confrontation. Staff are able to escort
individuals off of government property without further incident.
6:45 p.m.: As staff where preparing to transport an inmate to the
local hospital, protesters blocked the 2nd Avenue gate to prevent an
ambulance from entering the institution. Emergency response staff
were able to move the protesters back onto the street without further
incident.
Contractor continues work on installation of new temporary main
disconnect and removal of damaged wires from switchgear cabinet for
connection of new equipment.
Sunday, February 3, 2019
6:00 a.m.: Bureau of Prisons and Contract staff return to institution
to continue electrical service work. This work included installing
temporary service to switchgear #3 and making final electrical
BOP AFTER ACTION REPORT 013
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 14 of 31 PageID #: 1447
termination to the new temporary switchgear.
10:30 a.m.: Temperature readings in all units range between 67.6 and
77. Outside temperatures on February 3, 2019, range between 24 and
53.
12:29 p.m.: Two units returned to normal operation. These units were
not being disruptive and the institution determined it appropriate
to return these units to normal operation.
12:40 p.m. Protesters breach the West lobby and engage staff in a
physical altercation. Responding staff utilize physical force and
chemical agents to successfully remove the individuals. Seventeen
staff are injured as a result of this activity.
1:00 p.m.: All Units returned to lock down status.
2:00 p.m.: Staff begin institution tours:
Nydia Velazquez, U.S. Representative, New York 12th District;
Dan Wiley, Director for Representative Velazquez; Melissa Ortiz,
Community Relations Director, for Representative Velazquez.
4:08 p.m.: Protesters breach the 2nd Avenue gate. Responding staff
are able to remove the individuals without incident.
5:00 p.m.: Staff begin institution tour:
Richard R. Donoghue, U.S. Attorney, Eastern District of New York
6:30 p.m.: Emergency repairs finalized on the priority switch gear
destroyed in the fire and power fully restored to all areas of the
institution. All units return to normal operation.
The following Crisis Management Teams were activated: USP Canaan
Special Operations Response Team (SORT) – 19; MCC New York DCT - 10
Monday, February 4, 2019
7:00 a.m.: Protesters remain in front of institution.
8:00 a.m.: Legal Visiting schedule resumes.
10:45 a.m.: Bomb threat called into MDC. All visitors to the
institution were removed and institution was secured for an emergency
count. Law enforcement officials were notified and staff began to
BOP AFTER ACTION REPORT 014
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 15 of 31 PageID #: 1448
termination to the new temporary switchgear.
10:30 a.m.: Temperature readings in all units range between 67.6 and
77. Outside temperatures on February 3, 2019, range between 24 and
53.
12:29 p.m.: Two units returned to normal operation. These units were
not being disruptive and the institution determined it appropriate
to return these units to normal operation.
12:40 p.m. Protesters breach the West lobby and engage staff in a
physical altercation. Responding staff utilize physical force and
chemical agents to successfully remove the individuals. Seventeen
staff are injured as a result of this activity.
1:00 p.m.: All Units returned to lock down status.
2:00 p.m.: Staff begin institution tours:
Nydia Velazquez, U.S. Representative, New York 12th District;
Dan Wiley, Director for Representative Velazquez; Melissa Ortiz,
Community Relations Director, for Representative Velazquez.
4:08 p.m.: Protesters breach the 2nd Avenue gate. Responding staff
are able to remove the individuals without incident.
5:00 p.m.: Staff begin institution tour:
Richard R. Donoghue, U.S. Attorney, Eastern District of New York
6:30 p.m.: Emergency repairs finalized on the priority switch gear
destroyed in the fire and power fully restored to all areas of the
institution. All units return to normal operation.
The following Crisis Management Teams were activated: USP Canaan
Special Operations Response Team (SORT) – 19; MCC New York DCT - 10
Monday, February 4, 2019
7:00 a.m.: Protesters remain in front of institution.
8:00 a.m.: Legal Visiting schedule resumes.
10:45 a.m.: Bomb threat called into MDC. All visitors to the
institution were removed and institution was secured for an emergency
count. Law enforcement officials were notified and staff began to
BOP AFTER ACTION REPORT 014
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 15 of 31 PageID #: 1448
methodically search the interior and exterior of the institution.
1:50 p.m.: Bomb threat cleared.
2:00 p.m.: Institutions resumes normal operations, allowing inmates
access to unit common areas, showers, outdoor recreation, and hot
water dispensers. Visitation for legal and social visits resume
normal operation.
5:00 p.m.: FBI reports to institution. Notifies Warden of death
threats identified towards the following staff: Warden, Associate
Warden, and Correctional Officer.
6:00 p.m.: Nydia Velazquez, U.S. Representative, New York 12th
District; Dan Wiley, Director for Representative Velazquez; Melissa
Ortiz, Community Relations Director, for Representative Velazquez,
visit MDC Brooklyn.
Institution reports NYPD places barricades in front of the MDC
entrance; time of placement not documented.
Tuesday, February 5, 2019
7:00 a.m.: Protesters remain in front of institution, however,
institution is operating under normal procedures, providing inmates
access to all areas of unit, medical, and programming activities.
11:30 a.m.: Institution documentation reflects Command Center
activated.
5:10 p.m.: Staff begin institution tour:
Analisa Torres, U.S. District Judge, Southern District of New York
The following Crisis Management Teams were activated: MDC Brooklyn
Planning Section Team (PST); USP Canaan Emergency Preparedness
Officer (EPO); FCI Otisville DCT – 19;
Wednesday, February 6, 2019
The following Crisis Management Teams were activated: FMC Devens SORT
- 16.
BOP AFTER ACTION REPORT 015
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 16 of 31 PageID #: 1449
methodically search the interior and exterior of the institution.
1:50 p.m.: Bomb threat cleared.
2:00 p.m.: Institutions resumes normal operations, allowing inmates
access to unit common areas, showers, outdoor recreation, and hot
water dispensers. Visitation for legal and social visits resume
normal operation.
5:00 p.m.: FBI reports to institution. Notifies Warden of death
threats identified towards the following staff: Warden, Associate
Warden, and Correctional Officer.
6:00 p.m.: Nydia Velazquez, U.S. Representative, New York 12th
District; Dan Wiley, Director for Representative Velazquez; Melissa
Ortiz, Community Relations Director, for Representative Velazquez,
visit MDC Brooklyn.
Institution reports NYPD places barricades in front of the MDC
entrance; time of placement not documented.
Tuesday, February 5, 2019
7:00 a.m.: Protesters remain in front of institution, however,
institution is operating under normal procedures, providing inmates
access to all areas of unit, medical, and programming activities.
11:30 a.m.: Institution documentation reflects Command Center
activated.
5:10 p.m.: Staff begin institution tour:
Analisa Torres, U.S. District Judge, Southern District of New York
The following Crisis Management Teams were activated: MDC Brooklyn
Planning Section Team (PST); USP Canaan Emergency Preparedness
Officer (EPO); FCI Otisville DCT – 19;
Wednesday, February 6, 2019
The following Crisis Management Teams were activated: FMC Devens SORT
- 16.
BOP AFTER ACTION REPORT 015
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 16 of 31 PageID #: 1449
Thursday, February 7, 2019
The following Crisis Management Teams were activated: MDC Brooklyn
Crisis Support Team (CST) – 2; MCC New York CST – 5.
Friday, February 8, 2019
The following Crisis Management Teams were activated: FCI Otisville
CST – 2; FCI Danbury DCT – 17.
Monday, February 11, 2019
6:00 p.m.: Staff begin institution tour:
Doug Collins U.S. Representative, Georgia’s 9th District
The following Crisis Management Teams were activated: FDC
Philadelphia DCT - 19; USP Lewisburg EPO.
Wednesday, February 13, 2019
The following Crisis Management Teams were activated: FDC
Philadelphia EPO; FCC Allenwood EPO.
Wednesday, February 27, 2019
Miller-Remick, a structural engineering firm, submits an initial
report to the Northeast Regional Office outlining several potential
causes of the switchgear malfunction resulting in the fire. Report
suggest “incoming feeders were spliced inside the switchboard,
presumably when they were first installed”, and “feeders
were….insufficient length....lengthened via a taped butt splice”.
Friday, March 1, 2019
2:39 p.m.: NY Post issues article, titled “Inmates Again Without Heat
at Brooklyn Detention Center”. Article quotes Deirdre Von Dornum,
Federal Public Defenders Office, Eastern District of New York, who
reported the heat was out again in three units and “there’s freezing
air coming out of the vents”. On March 1, 2019, temperature readings
in all units range between 69.6 and 76.8.
BOP AFTER ACTION REPORT 016
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 17 of 31 PageID #: 1450
Thursday, February 7, 2019
The following Crisis Management Teams were activated: MDC Brooklyn
Crisis Support Team (CST) – 2; MCC New York CST – 5.
Friday, February 8, 2019
The following Crisis Management Teams were activated: FCI Otisville
CST – 2; FCI Danbury DCT – 17.
Monday, February 11, 2019
6:00 p.m.: Staff begin institution tour:
Doug Collins U.S. Representative, Georgia’s 9th District
The following Crisis Management Teams were activated: FDC
Philadelphia DCT - 19; USP Lewisburg EPO.
Wednesday, February 13, 2019
The following Crisis Management Teams were activated: FDC
Philadelphia EPO; FCC Allenwood EPO.
Wednesday, February 27, 2019
Miller-Remick, a structural engineering firm, submits an initial
report to the Northeast Regional Office outlining several potential
causes of the switchgear malfunction resulting in the fire. Report
suggest “incoming feeders were spliced inside the switchboard,
presumably when they were first installed”, and “feeders
were….insufficient length....lengthened via a taped butt splice”.
Friday, March 1, 2019
2:39 p.m.: NY Post issues article, titled “Inmates Again Without Heat
at Brooklyn Detention Center”. Article quotes Deirdre Von Dornum,
Federal Public Defenders Office, Eastern District of New York, who
reported the heat was out again in three units and “there’s freezing
air coming out of the vents”. On March 1, 2019, temperature readings
in all units range between 69.6 and 76.8.
BOP AFTER ACTION REPORT 016
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 17 of 31 PageID #: 1450
Analysis of Events:
The After Action Review Team discovered lapses of basic sound
correctional practices that diminished the institution’s ability to
effectively recognize, address, and respond to a potential
incident(s) from developing and/or occurring. Additionally, the
neglect of major mechanical systems at the MDC was noted as a
significant concern by subject matter experts on the review team.
Below are the key areas in which the team has based our findings.
Mechanical Services
A comprehensive review of the Facilities Department revealed neglect
of mechanical components that led to failures and breakdowns in major
equipment systems. The AAR team closely reviewed several key areas
that contributed to these failures, to include the preventative
maintenance program, condition of emergency power generators,
proficiency of staff, and the overall condition of the MDC mechanical
operations. During the week, the team, through direct observation,
determined there was a significant amount of mechanical neglect
throughout the building. Through observations and interviews, the
AAR Team concluded a lack of simple repairs and major system
deficiencies were noted with often no urgency to identify or correct
them in a timely fashion. Mechanical rooms and areas in which
mechanical systems are located were dirty and not maintained in a
high level of sanitation. A lack of these repairs can be directly
attributed to staff at MDC Brooklyn not submitting minor work
requests prior to these events. Without submission of work request,
the institution could not track completed and needed maintenance
work.
As noted in the chronological events, priority switch gear #3 began
experiencing problems on Friday, January 4, 2019, twenty-three days
prior to the fire and subsequent loss of power. Although, it is
difficult to identify the root cause of the electrical fire, it is
highly probable the switch gear and its two failures before the fire
were not properly assessed by staff or outside contractors prior to
making repairs on the system.
On Tuesday, January 29, 2019, the Northeast Regional Office hired
an architectural and structural engineering firm to assess the damage
caused by the fire and provide an analysis as to the probable causes
to the switchgear failure. The report identifies an arcing event,
which occurred inside the switchboard at the compartment containing
BOP AFTER ACTION REPORT 017
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 18 of 31 PageID #: 1451
Analysis of Events:
The After Action Review Team discovered lapses of basic sound
correctional practices that diminished the institution’s ability to
effectively recognize, address, and respond to a potential
incident(s) from developing and/or occurring. Additionally, the
neglect of major mechanical systems at the MDC was noted as a
significant concern by subject matter experts on the review team.
Below are the key areas in which the team has based our findings.
Mechanical Services
A comprehensive review of the Facilities Department revealed neglect
of mechanical components that led to failures and breakdowns in major
equipment systems. The AAR team closely reviewed several key areas
that contributed to these failures, to include the preventative
maintenance program, condition of emergency power generators,
proficiency of staff, and the overall condition of the MDC mechanical
operations. During the week, the team, through direct observation,
determined there was a significant amount of mechanical neglect
throughout the building. Through observations and interviews, the
AAR Team concluded a lack of simple repairs and major system
deficiencies were noted with often no urgency to identify or correct
them in a timely fashion. Mechanical rooms and areas in which
mechanical systems are located were dirty and not maintained in a
high level of sanitation. A lack of these repairs can be directly
attributed to staff at MDC Brooklyn not submitting minor work
requests prior to these events. Without submission of work request,
the institution could not track completed and needed maintenance
work.
As noted in the chronological events, priority switch gear #3 began
experiencing problems on Friday, January 4, 2019, twenty-three days
prior to the fire and subsequent loss of power. Although, it is
difficult to identify the root cause of the electrical fire, it is
highly probable the switch gear and its two failures before the fire
were not properly assessed by staff or outside contractors prior to
making repairs on the system.
On Tuesday, January 29, 2019, the Northeast Regional Office hired
an architectural and structural engineering firm to assess the damage
caused by the fire and provide an analysis as to the probable causes
to the switchgear failure. The report identifies an arcing event,
which occurred inside the switchboard at the compartment containing
BOP AFTER ACTION REPORT 017
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 18 of 31 PageID #: 1451
the input feeder cables. This event expelled enough energy to
carbonize the insulation on the cables and adjacent materials and
sparked a spontaneous fire. Both electrical feeders to the panel,
commercial and generator power, were damaged by the event.
A review of the report and physical inspection of the switchgear,
identified inconsistencies. Specifically, the report identified
that incoming feeder cables had been spliced inside the switchboard,
presumably when they were first installed. The report further
states that when the feeder cables were pulled into the switchboard
there was insufficient length to terminate them and as a remedy, they
were lengthened via a taped butt splice. An examination of the
cabinet and feeder cables did not show any evidence of splicing into
the switchgear cabinet. The damage caused by the fire was
catastrophic, resulting in irreparable conditions to the cabinet.
Based on this review, and regardless of the availability of emergency
power, restoring power to the affected areas was not possible.
Replacement parts for the cabinet and switchgear are not standard
items BOP institutions maintain, and are not standard items other
industrial or commercial buildings maintain as they rarely fail in
industry contexts.
The HVAC systems that provide air and heating to the inmate living
areas of the MDC are comprised of fifteen multi-staged air handling
units configured to introduce air and heat through hot and chilled
water coils. An examination of the systems revealed negligence in
maintaining the systems in operating order. At the time of the
review the HVAC systems servicing cells and day rooms of the housing
units were in the following condition:
23% (7 of 30) outside air dampers were found to have the motor
actuators disabled and/or disconnected.
53% (16 of 30) of the magnehelic (pressure) gauges were out of
commission.
100% (30 of 30) of the heating hot water recirculation pumps were
not working or had been removed.
3% (1 of 30) of the supply air fans was out of commission.
Overall, the systems were dirty and lacked the presence of regular
preventative maintenance.
BOP AFTER ACTION REPORT 018
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 19 of 31 PageID #: 1452
the input feeder cables. This event expelled enough energy to
carbonize the insulation on the cables and adjacent materials and
sparked a spontaneous fire. Both electrical feeders to the panel,
commercial and generator power, were damaged by the event.
A review of the report and physical inspection of the switchgear,
identified inconsistencies. Specifically, the report identified
that incoming feeder cables had been spliced inside the switchboard,
presumably when they were first installed. The report further
states that when the feeder cables were pulled into the switchboard
there was insufficient length to terminate them and as a remedy, they
were lengthened via a taped butt splice. An examination of the
cabinet and feeder cables did not show any evidence of splicing into
the switchgear cabinet. The damage caused by the fire was
catastrophic, resulting in irreparable conditions to the cabinet.
Based on this review, and regardless of the availability of emergency
power, restoring power to the affected areas was not possible.
Replacement parts for the cabinet and switchgear are not standard
items BOP institutions maintain, and are not standard items other
industrial or commercial buildings maintain as they rarely fail in
industry contexts.
The HVAC systems that provide air and heating to the inmate living
areas of the MDC are comprised of fifteen multi-staged air handling
units configured to introduce air and heat through hot and chilled
water coils. An examination of the systems revealed negligence in
maintaining the systems in operating order. At the time of the
review the HVAC systems servicing cells and day rooms of the housing
units were in the following condition:
23% (7 of 30) outside air dampers were found to have the motor
actuators disabled and/or disconnected.
53% (16 of 30) of the magnehelic (pressure) gauges were out of
commission.
100% (30 of 30) of the heating hot water recirculation pumps were
not working or had been removed.
3% (1 of 30) of the supply air fans was out of commission.
Overall, the systems were dirty and lacked the presence of regular
preventative maintenance.
BOP AFTER ACTION REPORT 018
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 19 of 31 PageID #: 1452
An assessment of the preventative maintenance program for the HVAC
systems revealed an absence of the following critical inspections
steps to ensure components are operating properly.
a. Recirculation pumps
b. Magnehelic Gauge readings
c. Damper actuators
d. Damper
Direct observations and interviews revealed an HVAC deficiency in
competency levels for some employees. The Bureau currently conducts
panel interviews for newly hired employees in trade positions (HVAC,
Electrical, etc.), but not for current BOP employees who apply and
are determined qualified by the reviewing officials. Several
discussions with staff yielded the absence of basic knowledge of
systems related to their field. Other observations and interviews
resulted in staff rationalizing the conditions and justifying why
systems were not repaired or maintained in accordance with
manufacturer standards. Furthermore, during the week of the AAR,
the review team witnessed employees from other institutions at MDC
assisting in repairs. These employees were working on HVAC
equipment, while MDC staff were noted in their shops/offices. The
inability to effect any significant improvement in the performance
of the department is directly associated with the culture of the
facility and lack of leadership and direction within the Facilities
Department.
During the review, the facilities department was staffed at 89.2%
with seven vacancies. These vacancies include two Electronics
Technicians, one Engineering Technician, one Electrical Worker
Foreman, one Maintenance Worker Foreman, one Plumbing Worker
Foreman, and one HVAC Foreman. Since the review, the institution has
hired two Electronics Technicians, one Engineering Technician, one
Maintenance Worker Foreman, and one Plumbing Worker Foreman.
Interviews were held the week of June 12, 2019, for one Electrician
and two additional Maintenance Worker Foreman. The HVAC Foreman
position has been announced multiple times. This position was
re-announced and closed June 26, 2019, and includes a 10% relocation
incentive. Although MDC staff noted the lack of sufficient staffing
as a primary reason for the issues noted above, the AAR team found
the staffing to be adequate to have prevented the neglect that
contributed to the general condition of the building. Additionally,
a department that is responsible for maintaining three buildings
(East, West and Staff Housing), only employs 23 inmate workers,
compared to the 34 staff. The amount of inmate workers is
BOP AFTER ACTION REPORT 019
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 20 of 31 PageID #: 1453
An assessment of the preventative maintenance program for the HVAC
systems revealed an absence of the following critical inspections
steps to ensure components are operating properly.
a. Recirculation pumps
b. Magnehelic Gauge readings
c. Damper actuators
d. Damper
Direct observations and interviews revealed an HVAC deficiency in
competency levels for some employees. The Bureau currently conducts
panel interviews for newly hired employees in trade positions (HVAC,
Electrical, etc.), but not for current BOP employees who apply and
are determined qualified by the reviewing officials. Several
discussions with staff yielded the absence of basic knowledge of
systems related to their field. Other observations and interviews
resulted in staff rationalizing the conditions and justifying why
systems were not repaired or maintained in accordance with
manufacturer standards. Furthermore, during the week of the AAR,
the review team witnessed employees from other institutions at MDC
assisting in repairs. These employees were working on HVAC
equipment, while MDC staff were noted in their shops/offices. The
inability to effect any significant improvement in the performance
of the department is directly associated with the culture of the
facility and lack of leadership and direction within the Facilities
Department.
During the review, the facilities department was staffed at 89.2%
with seven vacancies. These vacancies include two Electronics
Technicians, one Engineering Technician, one Electrical Worker
Foreman, one Maintenance Worker Foreman, one Plumbing Worker
Foreman, and one HVAC Foreman. Since the review, the institution has
hired two Electronics Technicians, one Engineering Technician, one
Maintenance Worker Foreman, and one Plumbing Worker Foreman.
Interviews were held the week of June 12, 2019, for one Electrician
and two additional Maintenance Worker Foreman. The HVAC Foreman
position has been announced multiple times. This position was
re-announced and closed June 26, 2019, and includes a 10% relocation
incentive. Although MDC staff noted the lack of sufficient staffing
as a primary reason for the issues noted above, the AAR team found
the staffing to be adequate to have prevented the neglect that
contributed to the general condition of the building. Additionally,
a department that is responsible for maintaining three buildings
(East, West and Staff Housing), only employs 23 inmate workers,
compared to the 34 staff. The amount of inmate workers is
BOP AFTER ACTION REPORT 019
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 20 of 31 PageID #: 1453
insufficient to accomplish the maintenance of these buildings. A
review of this issue suggested the Unit Team Staff were not assigning
or referring inmates to work details within the Facilities Department
and Facilities Staff indicated during interviews that did not have
the desire or time to supervise inmate work details.
The review team was unable to confirm the MDC conducted an annual
building and grounds inspection as no report was produced. This
report is completed annually as a self assessment of all facility
structures and systems, to include HVAC. The Facility Manager is
responsible to complete this assessment (PS 4200.12, Chapter 5, page
4). The missing inspection should have identified the issues with
the HVAC system and speaks to a broken preventative maintenance
program. The Buildings and Grounds inspection used to be reviewed
as part of the Program Review process. It required submission to
Regional Office for review and a response was generated to the report.
This requirement was removed during the policy update in April 2016.
Funding is an essential requirement in maintaining the facilities
departments’ mission. A review of annual funding levels along with
requests supplemental funding for projects and emergency repairs,
revealed sufficient funding and support from the Regional Office.
The agency utilizes a variety of internal controls to ensure
functions of a department are meeting standards based on regulations
and policy. The review team closely examined documents pertaining
to Regional Staff Assist Visits, Operations Reviews, and Program
Reviews. Internal reviews were completed as noted below.
Program Review – March 29, 2016
Operational Review – May 1-5, 2017
Operational Review – May 21-25, 2018
Regional Staff Assist Visit – July 30 - August 2, 2018
Based on the teams observations, these did not identify failures in
a vital area. Specifically, the Facilities Management Program
Review Guidelines (G4200I.08) dated, 10/27/17, Section (3.1)
Preventative Maintenance (PM) Program lists the following.
3.1.1 (V-3) Tour the institution(s) and:
a. Make a visual assessment of the physical plant and infrastructure
(buildings, mechanical rooms, grounds, tunnels, vaults, roofs,
telephone rooms, etc.) and determine if PM and/or corrective
maintenance is accomplished.
BOP AFTER ACTION REPORT 020
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 21 of 31 PageID #: 1454
insufficient to accomplish the maintenance of these buildings. A
review of this issue suggested the Unit Team Staff were not assigning
or referring inmates to work details within the Facilities Department
and Facilities Staff indicated during interviews that did not have
the desire or time to supervise inmate work details.
The review team was unable to confirm the MDC conducted an annual
building and grounds inspection as no report was produced. This
report is completed annually as a self assessment of all facility
structures and systems, to include HVAC. The Facility Manager is
responsible to complete this assessment (PS 4200.12, Chapter 5, page
4). The missing inspection should have identified the issues with
the HVAC system and speaks to a broken preventative maintenance
program. The Buildings and Grounds inspection used to be reviewed
as part of the Program Review process. It required submission to
Regional Office for review and a response was generated to the report.
This requirement was removed during the policy update in April 2016.
Funding is an essential requirement in maintaining the facilities
departments’ mission. A review of annual funding levels along with
requests supplemental funding for projects and emergency repairs,
revealed sufficient funding and support from the Regional Office.
The agency utilizes a variety of internal controls to ensure
functions of a department are meeting standards based on regulations
and policy. The review team closely examined documents pertaining
to Regional Staff Assist Visits, Operations Reviews, and Program
Reviews. Internal reviews were completed as noted below.
Program Review – March 29, 2016
Operational Review – May 1-5, 2017
Operational Review – May 21-25, 2018
Regional Staff Assist Visit – July 30 - August 2, 2018
Based on the teams observations, these did not identify failures in
a vital area. Specifically, the Facilities Management Program
Review Guidelines (G4200I.08) dated, 10/27/17, Section (3.1)
Preventative Maintenance (PM) Program lists the following.
3.1.1 (V-3) Tour the institution(s) and:
a. Make a visual assessment of the physical plant and infrastructure
(buildings, mechanical rooms, grounds, tunnels, vaults, roofs,
telephone rooms, etc.) and determine if PM and/or corrective
maintenance is accomplished.
BOP AFTER ACTION REPORT 020
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 21 of 31 PageID #: 1454
b. Check the condition of equipment in areas toured to determine if
PM has been accomplished and equipment is in good working order.
The internal reviews failed to identify the negligence pertaining
to the HVAC system and failures to conduct repairs to essential
components. Documents and interviews reflect a majority of the
issues identified in the previous section are long standing issues.
Interviews with facilities management staff indicated that several
of the inoperable components on the HVAC system have been
disconnected and/or removed for several years and should have been
reflected in the internal audits identified above.
Communication with the media and external stakeholders
Effective communications during a critical incident is essential in
maintaining a quick resolution to crisis events. The review team
closely examined several key areas of communication that contributed
to the stakeholder and community activists’ responses to this
incident. These areas include staff briefings, inmate
communications, responsiveness to media requests, and maintaining
open lines of communications with the courts, law enforcement
agencies, U.S. Attorney’s Offices, Federal Public Defenders, and
private attorneys.
Staff and inmates were provided with limited information regarding
the status of repairs and current operations of the facility. There
were three documented staff conference calls (2/2, 2/4, 2/5) and one
staff briefing. The team was able to discover one written bulletin
to the population but were unable to confirm the information was
effectively communicated with all inmates at the MDC. Interviews
with staff revealed complaints that little to no information was
disseminated to them on a daily basis regarding active threats to
staff safety and intelligence regarding protesters. Ensuring staff
are provided up to date information during a crisis situation is
paramount in coordinating resources and accomplishing tasks related
to a successful resolution.
Throughout this incident the BOP received a total of 128 media
inquiries. Nineteen were direct inquiries to the institution from
media outlets, requesting information pertaining to the partial loss
of power and reported heating outage. A close examination revealed
some responses in providing current information were not done in a
BOP AFTER ACTION REPORT 021
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 22 of 31 PageID #: 1455
b. Check the condition of equipment in areas toured to determine if
PM has been accomplished and equipment is in good working order.
The internal reviews failed to identify the negligence pertaining
to the HVAC system and failures to conduct repairs to essential
components. Documents and interviews reflect a majority of the
issues identified in the previous section are long standing issues.
Interviews with facilities management staff indicated that several
of the inoperable components on the HVAC system have been
disconnected and/or removed for several years and should have been
reflected in the internal audits identified above.
Communication with the media and external stakeholders
Effective communications during a critical incident is essential in
maintaining a quick resolution to crisis events. The review team
closely examined several key areas of communication that contributed
to the stakeholder and community activists’ responses to this
incident. These areas include staff briefings, inmate
communications, responsiveness to media requests, and maintaining
open lines of communications with the courts, law enforcement
agencies, U.S. Attorney’s Offices, Federal Public Defenders, and
private attorneys.
Staff and inmates were provided with limited information regarding
the status of repairs and current operations of the facility. There
were three documented staff conference calls (2/2, 2/4, 2/5) and one
staff briefing. The team was able to discover one written bulletin
to the population but were unable to confirm the information was
effectively communicated with all inmates at the MDC. Interviews
with staff revealed complaints that little to no information was
disseminated to them on a daily basis regarding active threats to
staff safety and intelligence regarding protesters. Ensuring staff
are provided up to date information during a crisis situation is
paramount in coordinating resources and accomplishing tasks related
to a successful resolution.
Throughout this incident the BOP received a total of 128 media
inquiries. Nineteen were direct inquiries to the institution from
media outlets, requesting information pertaining to the partial loss
of power and reported heating outage. A close examination revealed
some responses in providing current information were not done in a
BOP AFTER ACTION REPORT 021
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 22 of 31 PageID #: 1455
timely matter. The average response time to these inquiries was
calculated at 16.2 hours before a response was returned to the sender.
In the current environment of technology and social media, the lack
of quick response to inquiries only hinders the agency in
deescalating situations, distracts from providing a transparent
environment, and leads to increased levels of inaccurate information
being shared by other sources. The current practice of the Bureau
of Prisons is to have Regional and Central Office review all media
inquiries prior to issuance to requesting media outlets.
Maintaining open lines of communications with our federal partners
is critical in accomplishing the mission at the MDC. Interviews with
members of the courts, law enforcement agencies,
U.S. Attorney’s Offices, Federal Public Defenders and private
attorneys, revealed a failure in providing information regarding the
MDC’s mechanical issues and status of repairs.
Many of these entities provided favorable comments regarding the
working relationship with the MDC but indicated that they were not
kept informed throughout the incident. These individuals relayed
the lack of transparency resulted in significant delays in court
proceedings, scheduling conflicts, and having to dedicate additional
resources to respond to inquiries and complaints. Overall, they
indicated that the manner in which the MDC handled this incident
demonstrated a lack of transparency, communication, and some
questioned the truthfulness of the information being provided.
The MDC does not have an updated media plan that outlines national
policy requirements. The lack of a comprehensive plan only
distracts from the MDC’s ability to disseminate critical information
in an emergency situation. Furthermore, the MDC did not have readily
available contact information for all essential agencies. The
absence of establishing good communications directly impacted the
institution’s ability to accomplish the mission during this incident
and resulted in inaccurate or exaggerated reports being spread in
community and social media forums.
Legal Services
Following interviews and observations, the review team found an
overall lack of effective communication, which adversely effected
the MDC’s ability to provide timely, accurate information to the
courts, Federal Public Defenders Office, and private attorneys. The
institution’s Executive Staff and Legal Department failed to share
BOP AFTER ACTION REPORT 022
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 23 of 31 PageID #: 1456
timely matter. The average response time to these inquiries was
calculated at 16.2 hours before a response was returned to the sender.
In the current environment of technology and social media, the lack
of quick response to inquiries only hinders the agency in
deescalating situations, distracts from providing a transparent
environment, and leads to increased levels of inaccurate information
being shared by other sources. The current practice of the Bureau
of Prisons is to have Regional and Central Office review all media
inquiries prior to issuance to requesting media outlets.
Maintaining open lines of communications with our federal partners
is critical in accomplishing the mission at the MDC. Interviews with
members of the courts, law enforcement agencies,
U.S. Attorney’s Offices, Federal Public Defenders and private
attorneys, revealed a failure in providing information regarding the
MDC’s mechanical issues and status of repairs.
Many of these entities provided favorable comments regarding the
working relationship with the MDC but indicated that they were not
kept informed throughout the incident. These individuals relayed
the lack of transparency resulted in significant delays in court
proceedings, scheduling conflicts, and having to dedicate additional
resources to respond to inquiries and complaints. Overall, they
indicated that the manner in which the MDC handled this incident
demonstrated a lack of transparency, communication, and some
questioned the truthfulness of the information being provided.
The MDC does not have an updated media plan that outlines national
policy requirements. The lack of a comprehensive plan only
distracts from the MDC’s ability to disseminate critical information
in an emergency situation. Furthermore, the MDC did not have readily
available contact information for all essential agencies. The
absence of establishing good communications directly impacted the
institution’s ability to accomplish the mission during this incident
and resulted in inaccurate or exaggerated reports being spread in
community and social media forums.
Legal Services
Following interviews and observations, the review team found an
overall lack of effective communication, which adversely effected
the MDC’s ability to provide timely, accurate information to the
courts, Federal Public Defenders Office, and private attorneys. The
institution’s Executive Staff and Legal Department failed to share
BOP AFTER ACTION REPORT 022
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 23 of 31 PageID #: 1456
information with each other on a daily basis, resulting limited
information sharing with our federal partners. The lack of trust
between the Legal Department and inmate’s attorneys was noted as
problematic and compounded information sharing and general
communication problems that resulted in inaccurate or exaggerated
reports being relayed into the community. This conclusion was based
on interviews and feedback from both BOP attorneys and Federal Public
Defender Attorneys.
Throughout the incident, legal visits were cancelled and/or
significantly curtailed based on the lack of power to the visiting
room. The review team estimates that approximately thirty attorney
visits occur daily and each attorney schedules multiple client
meetings. This function of the MDC is essential in accomplishing
the mission of the courts. The institution took additional measures
to place emergency lighting in several areas of the building, but
failed to recognize the significance of restoring attorney-client
visiting as soon as possible. The MDC should have utilized the
visiting room in the east building by providing security escorts and
temporary lighting in the walkway between both buildings.
The ability for inmates to place legal calls was reviewed, and
determined not to pose a significant concern. Inmates were able to
utilize the direct phone station in each housing unit to communicate
with the Federal Public Defenders Office. However, the review team
was unable to verify inmates who are not represented by the Federal
Public Defenders Office had adequate access to legal calls.
Nevertheless, access to legal calls was not noted as a concern during
interviews with inmates.
During a comprehensive meeting with the Federal Public Defender, a
number of concerns were discussed regarding the relationship between
agencies. An overall lack of faith was expressed regarding issues
pertaining to medical treatment, legal visits, wait times,
communications, professionalism of staff, responsiveness to issues,
and the lack of heating and lighting at the MDC. An overall concern
was the long standing culture of the MDC and its inability to serve
the Eastern and Southern Districts in accomplishing the mission of
the courts. It was relayed that attorneys do not complain about
problems at the institution because they fear retaliation towards
their clients. Examples given included such actions as leaving
attorneys waiting in the lobby for extended periods of time and
locking attorney rooms with the lights off and indicating the lights
don’t work, making them unavailable.
BOP AFTER ACTION REPORT 023
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 24 of 31 PageID #: 1457
information with each other on a daily basis, resulting limited
information sharing with our federal partners. The lack of trust
between the Legal Department and inmate’s attorneys was noted as
problematic and compounded information sharing and general
communication problems that resulted in inaccurate or exaggerated
reports being relayed into the community. This conclusion was based
on interviews and feedback from both BOP attorneys and Federal Public
Defender Attorneys.
Throughout the incident, legal visits were cancelled and/or
significantly curtailed based on the lack of power to the visiting
room. The review team estimates that approximately thirty attorney
visits occur daily and each attorney schedules multiple client
meetings. This function of the MDC is essential in accomplishing
the mission of the courts. The institution took additional measures
to place emergency lighting in several areas of the building, but
failed to recognize the significance of restoring attorney-client
visiting as soon as possible. The MDC should have utilized the
visiting room in the east building by providing security escorts and
temporary lighting in the walkway between both buildings.
The ability for inmates to place legal calls was reviewed, and
determined not to pose a significant concern. Inmates were able to
utilize the direct phone station in each housing unit to communicate
with the Federal Public Defenders Office. However, the review team
was unable to verify inmates who are not represented by the Federal
Public Defenders Office had adequate access to legal calls.
Nevertheless, access to legal calls was not noted as a concern during
interviews with inmates.
During a comprehensive meeting with the Federal Public Defender, a
number of concerns were discussed regarding the relationship between
agencies. An overall lack of faith was expressed regarding issues
pertaining to medical treatment, legal visits, wait times,
communications, professionalism of staff, responsiveness to issues,
and the lack of heating and lighting at the MDC. An overall concern
was the long standing culture of the MDC and its inability to serve
the Eastern and Southern Districts in accomplishing the mission of
the courts. It was relayed that attorneys do not complain about
problems at the institution because they fear retaliation towards
their clients. Examples given included such actions as leaving
attorneys waiting in the lobby for extended periods of time and
locking attorney rooms with the lights off and indicating the lights
don’t work, making them unavailable.
BOP AFTER ACTION REPORT 023
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 24 of 31 PageID #: 1457
Direct observations by the review team revealed an ineffective method
to process visitors into the institution and confirmed that wait
times were sometimes unnecessary. Additionally, a review of the
visiting room during legal visits also confirmed the lack of
responsiveness on behalf of staff pertaining to issues raised by
attorneys.
Lastly, the BOP Legal Services Department did not receive timely
responses to its repeated inquires to the Executive Staff. Legal
Services was not privy to the steps being taken to resolve the
incident and several questions went unanswered. Internal
cooperation and communications failed to ensure all parties were
circulating accurate information to resolve the incident.
Medical and Mental Health Treatment
The Health Services Unit (HSU) is staffed at 76% with three newly
hired BOP staff physicians, five Advanced Practice Providers (APPs),
and six registered nurses (RNs). Team medicine is implemented with
the APPs assigned to specific floors to provide medical services.
During the electrical power outage on January 27, 2019, the HSU
remained operational with the provision of sick call triage, chronic
care clinics, emergency services, and medication administration.
The facility conducts two pill lines on each floor at 6:00 a.m., 2:00
p.m., Monday -Friday, and 7:00 a.m., and 4:00 p.m. on Saturdays and
Sundays.
Sick call triage is conducted electronically through the Trust Fund
Limited Inmate Computer System (TRULINCS). Inmates submit requests
by email to staff BRO/Inmatetosickcall (Medical) or
BRO/Inmatetodental (Dental) mailboxes. During the electrical
outage, inmates had to submit sick call and medication refill
requests via paper to the medical staff. The medical staff were able
to triage medical services based on medical acuity. Medication
refills were processed by paper requests or by submitting empty
medication bottles to the medical staff.
During the review, it was noted that the electronic sick call process
as performed, may not always meet the requirements of the Patient
Care Program Statement 6031.04 and lacks the appropriate ongoing
oversight for triage purposes. For example, clinically indicated
vital signs may not have been taken for an individual with a poor
clinical presentation. This is because the request was not reviewed
and appropriately assigned to a clinical provider to make a
BOP AFTER ACTION REPORT 024
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 25 of 31 PageID #: 1458
Direct observations by the review team revealed an ineffective method
to process visitors into the institution and confirmed that wait
times were sometimes unnecessary. Additionally, a review of the
visiting room during legal visits also confirmed the lack of
responsiveness on behalf of staff pertaining to issues raised by
attorneys.
Lastly, the BOP Legal Services Department did not receive timely
responses to its repeated inquires to the Executive Staff. Legal
Services was not privy to the steps being taken to resolve the
incident and several questions went unanswered. Internal
cooperation and communications failed to ensure all parties were
circulating accurate information to resolve the incident.
Medical and Mental Health Treatment
The Health Services Unit (HSU) is staffed at 76% with three newly
hired BOP staff physicians, five Advanced Practice Providers (APPs),
and six registered nurses (RNs). Team medicine is implemented with
the APPs assigned to specific floors to provide medical services.
During the electrical power outage on January 27, 2019, the HSU
remained operational with the provision of sick call triage, chronic
care clinics, emergency services, and medication administration.
The facility conducts two pill lines on each floor at 6:00 a.m., 2:00
p.m., Monday -Friday, and 7:00 a.m., and 4:00 p.m. on Saturdays and
Sundays.
Sick call triage is conducted electronically through the Trust Fund
Limited Inmate Computer System (TRULINCS). Inmates submit requests
by email to staff BRO/Inmatetosickcall (Medical) or
BRO/Inmatetodental (Dental) mailboxes. During the electrical
outage, inmates had to submit sick call and medication refill
requests via paper to the medical staff. The medical staff were able
to triage medical services based on medical acuity. Medication
refills were processed by paper requests or by submitting empty
medication bottles to the medical staff.
During the review, it was noted that the electronic sick call process
as performed, may not always meet the requirements of the Patient
Care Program Statement 6031.04 and lacks the appropriate ongoing
oversight for triage purposes. For example, clinically indicated
vital signs may not have been taken for an individual with a poor
clinical presentation. This is because the request was not reviewed
and appropriately assigned to a clinical provider to make a
BOP AFTER ACTION REPORT 024
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 25 of 31 PageID #: 1458
determination regarding the clinical necessity for vital signs to
be obtained.
The APPs and nurses are both reviewing and scheduling sick call
appointments. A review of 219 sick call requests between February
8–12, 2019, revealed three requests had been opened by medical staff.
The sample review may be a reflection of lack of oversight of the
sick call electronic mailbox.
During the limited electrical outage, Health Services Unit
identified 14 inmates diagnosed with sleep apnea requiring
electrical outlets for the CPAP machine. Due to the electrical
outage it was recommended to transfer the inmates with CPAP machines
to the East building. The inmates were transferred to the East
building on January 31, 2019, five days after the loss of power.
There were three inmates out of the fourteen who declined to move
and remained in the West building. Based on their medical condition,
it would have been prudent to move them and not given the option to
remain in their current housing unit.
Interviews with a staff psychologists revealed increased clinical
intervention in February with 162 visits compared to January with
74 visits. Psychologists or the contract psychiatrists addressed
mental health concerns voiced by the inmate population during the
incident and provided comprehensive and adequate mental health
treatment without any concerns noted during the review.
Twenty-eight patients voiced medical and psychiatric complaints
during the Federal Public Defenders visit on Friday,
February 1, 2019. Electronic health record reviews were conducted
on patients with medical complaints identified during the visit and
the clinical outcomes were all properly documented. The Bureau
Electronic Medical Records (BEMR) review revealed two inmates with
court-ordered emergency treatment. Both were provided medical
treatment and returned from the community hospital to the facility
within 24 hours. In addition, four patients with medical complaints
were transported to the community hospital to receive medical care.
The majority of the patients with medical complaints were classified
as care level one or care level two with only one patient with multiple
uncontrolled co-morbidities classified as care level 3.
Medical staff were responsive to the medical needs of the patient
population during the incident and referred those patients to the
community hospital who required urgent and emergency care. The
medical staff addressed all of the patient’s medical complaints
BOP AFTER ACTION REPORT 025
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 26 of 31 PageID #: 1459
determination regarding the clinical necessity for vital signs to
be obtained.
The APPs and nurses are both reviewing and scheduling sick call
appointments. A review of 219 sick call requests between February
8–12, 2019, revealed three requests had been opened by medical staff.
The sample review may be a reflection of lack of oversight of the
sick call electronic mailbox.
During the limited electrical outage, Health Services Unit
identified 14 inmates diagnosed with sleep apnea requiring
electrical outlets for the CPAP machine. Due to the electrical
outage it was recommended to transfer the inmates with CPAP machines
to the East building. The inmates were transferred to the East
building on January 31, 2019, five days after the loss of power.
There were three inmates out of the fourteen who declined to move
and remained in the West building. Based on their medical condition,
it would have been prudent to move them and not given the option to
remain in their current housing unit.
Interviews with a staff psychologists revealed increased clinical
intervention in February with 162 visits compared to January with
74 visits. Psychologists or the contract psychiatrists addressed
mental health concerns voiced by the inmate population during the
incident and provided comprehensive and adequate mental health
treatment without any concerns noted during the review.
Twenty-eight patients voiced medical and psychiatric complaints
during the Federal Public Defenders visit on Friday,
February 1, 2019. Electronic health record reviews were conducted
on patients with medical complaints identified during the visit and
the clinical outcomes were all properly documented. The Bureau
Electronic Medical Records (BEMR) review revealed two inmates with
court-ordered emergency treatment. Both were provided medical
treatment and returned from the community hospital to the facility
within 24 hours. In addition, four patients with medical complaints
were transported to the community hospital to receive medical care.
The majority of the patients with medical complaints were classified
as care level one or care level two with only one patient with multiple
uncontrolled co-morbidities classified as care level 3.
Medical staff were responsive to the medical needs of the patient
population during the incident and referred those patients to the
community hospital who required urgent and emergency care. The
medical staff addressed all of the patient’s medical complaints
BOP AFTER ACTION REPORT 025
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 26 of 31 PageID #: 1459
voiced during the FPD visit by Thursday, February 7, 2019. During
the FPD visit, general concerns expressed pertained to the inmate’s
inability to make requests for medical service and/or medication
refills through the Trust Fund Limited Inmate Computer System
(TRULINCS) during the electrical outage. The Health Services
Administrator stated the inmates were instructed to access medical
services by submitting a written request to health services for
evaluation or medication refills as described in the Inmate Admission
and Orientation Handbook. In addition, he conveyed the patients were
able to submit empty medication bottles to medical staff for
medication refills. Pill line administration of medications on each
unit continued uninterrupted during the power outage
Emergency Response
Based on the external threat to the institution and growing crowds
of protesters, the institution activated several emergency response
protocols to address the potential threats to staff and institution
safety and security. Temporary modifications were made by
installing cyclone fencing in front of the facility to prevent direct
access by protesters. Additionally, Crisis Management Teams (CMT)
from nine institutions, totaling ninety-five staff, were deployed
to the MDC throughout the incident.
The review team revealed multiple lapses in policy and procedures,
related to training, equipment, documentation of activities, that
diminished the institution’s ability to avoid the incident in the
lobby on Sunday, February 3, 2019. Staff failed to anticipate the
potential conflict and did not secure the main egress to the facility.
CMT teams were activated and on standby but staff were not wearing
required gear. Several CMT members lack the mandatory training
requirements and contingency plans have not been reviewed by all full
time employees. In addition, the Command Center was not established
in a timely matter and initially only maintained limited
documentation of the activities in and surrounding the institution.
When questioned, staff were not proficient in the Use of Force policy
and arrest authority. Executive leadership in the institution were
not aware of the exclusive jurisdiction of MDC and the institution’s
ultimate responsibility for law enforcement functions on government
property. Historically, the New York Police Department (NYPD) had
effectuated arrests of visitors at the MDC for a variety of offenses.
Once it determined the MDC is under exclusive federal jurisdiction,
the NYPD gave orders to not access MDC property to effectuate arrests.
BOP AFTER ACTION REPORT 026
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 27 of 31 PageID #: 1460
voiced during the FPD visit by Thursday, February 7, 2019. During
the FPD visit, general concerns expressed pertained to the inmate’s
inability to make requests for medical service and/or medication
refills through the Trust Fund Limited Inmate Computer System
(TRULINCS) during the electrical outage. The Health Services
Administrator stated the inmates were instructed to access medical
services by submitting a written request to health services for
evaluation or medication refills as described in the Inmate Admission
and Orientation Handbook. In addition, he conveyed the patients were
able to submit empty medication bottles to medical staff for
medication refills. Pill line administration of medications on each
unit continued uninterrupted during the power outage
Emergency Response
Based on the external threat to the institution and growing crowds
of protesters, the institution activated several emergency response
protocols to address the potential threats to staff and institution
safety and security. Temporary modifications were made by
installing cyclone fencing in front of the facility to prevent direct
access by protesters. Additionally, Crisis Management Teams (CMT)
from nine institutions, totaling ninety-five staff, were deployed
to the MDC throughout the incident.
The review team revealed multiple lapses in policy and procedures,
related to training, equipment, documentation of activities, that
diminished the institution’s ability to avoid the incident in the
lobby on Sunday, February 3, 2019. Staff failed to anticipate the
potential conflict and did not secure the main egress to the facility.
CMT teams were activated and on standby but staff were not wearing
required gear. Several CMT members lack the mandatory training
requirements and contingency plans have not been reviewed by all full
time employees. In addition, the Command Center was not established
in a timely matter and initially only maintained limited
documentation of the activities in and surrounding the institution.
When questioned, staff were not proficient in the Use of Force policy
and arrest authority. Executive leadership in the institution were
not aware of the exclusive jurisdiction of MDC and the institution’s
ultimate responsibility for law enforcement functions on government
property. Historically, the New York Police Department (NYPD) had
effectuated arrests of visitors at the MDC for a variety of offenses.
Once it determined the MDC is under exclusive federal jurisdiction,
the NYPD gave orders to not access MDC property to effectuate arrests.
BOP AFTER ACTION REPORT 026
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 27 of 31 PageID #: 1460
An assessment of the MDC and its external gates, doors, and egresses
revealed several deficiencies. The front lobby doors have not been
properly secure for several months. The vehicle gate was damaged
and had been neglected until this emergency. The roll-up vehicle
gate that accesses the trash compactor area has not been repaired
for over a year. Based on interviews, observations, and
documentation, the overall condition of the security features
surrounding the facility are poor and require extensive repairs.
Maintaining accurate and comprehensive incident documentation is
essential in an emergency. The institution initially struggled to
compile data related to Planning Section duties. An experienced CMT
member from another institution was deployed to the MDC to assist
in implementing the Incident Command System. The institution has
four members assigned to the Planning Section Team and not all members
have completed the required ICS training and quarterly team training.
During the fire on Sunday, January 27, 2019, responding staff
accessed and deployed the Self Contained Breathing Apparatus (SCBA)
to enter the 2nd mechanical room. Five staff were identified as
utilizing the equipment and none of the staff were fit tested and
one of five never received any SCBA certification training. A review
of the SCBA storage locations revealed several units missing and
unaccounted for.
Search Procedures
During the incident inmates were broadcasting information from
contraband cell phones to several social media sites. Information
provided by institution staff revealed that a total of fifteen
contraband cell phones had been discovered in a 90 day time frame
within the secure confines of the MDC. An assessment and observation
of the front lobby and rear gate revealed disregard for security
procedures. During the review week, MDC staff failed to properly
search, identify, and document the team as they entered the facility.
Adequate searches were not conducted at the rear gate. The
configuration of the front lobby is ineffective and allows for staff
and visitors to circumvent comprehensive search procedures.
BOP AFTER ACTION REPORT 027
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 28 of 31 PageID #: 1461
An assessment of the MDC and its external gates, doors, and egresses
revealed several deficiencies. The front lobby doors have not been
properly secure for several months. The vehicle gate was damaged
and had been neglected until this emergency. The roll-up vehicle
gate that accesses the trash compactor area has not been repaired
for over a year. Based on interviews, observations, and
documentation, the overall condition of the security features
surrounding the facility are poor and require extensive repairs.
Maintaining accurate and comprehensive incident documentation is
essential in an emergency. The institution initially struggled to
compile data related to Planning Section duties. An experienced CMT
member from another institution was deployed to the MDC to assist
in implementing the Incident Command System. The institution has
four members assigned to the Planning Section Team and not all members
have completed the required ICS training and quarterly team training.
During the fire on Sunday, January 27, 2019, responding staff
accessed and deployed the Self Contained Breathing Apparatus (SCBA)
to enter the 2nd mechanical room. Five staff were identified as
utilizing the equipment and none of the staff were fit tested and
one of five never received any SCBA certification training. A review
of the SCBA storage locations revealed several units missing and
unaccounted for.
Search Procedures
During the incident inmates were broadcasting information from
contraband cell phones to several social media sites. Information
provided by institution staff revealed that a total of fifteen
contraband cell phones had been discovered in a 90 day time frame
within the secure confines of the MDC. An assessment and observation
of the front lobby and rear gate revealed disregard for security
procedures. During the review week, MDC staff failed to properly
search, identify, and document the team as they entered the facility.
Adequate searches were not conducted at the rear gate. The
configuration of the front lobby is ineffective and allows for staff
and visitors to circumvent comprehensive search procedures.
BOP AFTER ACTION REPORT 027
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 28 of 31 PageID #: 1461
Mutual Agreements
The institution does not have mutual agreements with other agencies
to assist in emergency situations. Collaborative relationships
must be established to discuss and plan for emergencies and what
resources agencies are willing to provide in crisis situations.
CONCLUSIONS:
Based on the review, the team finds that while the cause of the fire
and loss of power to the MDC is currently under review, the actions,
decisions, and management of the maintenance of the building was
noted as problematic. The condition of the MDC is poor and requires
extensive preventative maintenance to restore these mechanical
systems. Additionally, many of the findings by the team were
associated with the failure to effectively communicate with staff,
inmates, external stakeholders, and the courts surrounding the
events at the MDC. Public perception into the loss of electricity
and heat was not adequately addressed to avoid a civil disturbance
at the institution. Heating issues related to areas of the building
that house inmates was corrected prior to the power outage, however,
public perception fueled by lack of transparency outweighed the
facts. In addition, staff were not appropriately prepared to
respond to the civil disturbance emergency that occurred.
RECOMMENDATIONS:
BOP AFTER ACTION REPORT 028
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 29 of 31 PageID #: 1462
Mutual Agreements
The institution does not have mutual agreements with other agencies
to assist in emergency situations. Collaborative relationships
must be established to discuss and plan for emergencies and what
resources agencies are willing to provide in crisis situations.
CONCLUSIONS:
Based on the review, the team finds that while the cause of the fire
and loss of power to the MDC is currently under review, the actions,
decisions, and management of the maintenance of the building was
noted as problematic. The condition of the MDC is poor and requires
extensive preventative maintenance to restore these mechanical
systems. Additionally, many of the findings by the team were
associated with the failure to effectively communicate with staff,
inmates, external stakeholders, and the courts surrounding the
events at the MDC. Public perception into the loss of electricity
and heat was not adequately addressed to avoid a civil disturbance
at the institution. Heating issues related to areas of the building
that house inmates was corrected prior to the power outage, however,
public perception fueled by lack of transparency outweighed the
facts. In addition, staff were not appropriately prepared to
respond to the civil disturbance emergency that occurred.
RECOMMENDATIONS:
BOP AFTER ACTION REPORT 028
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 29 of 31 PageID #: 1462
BOP AFTER ACTION REPORT 029
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 30 of 31 PageID #: 1463
BOP AFTER ACTION REPORT 029
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 30 of 31 PageID #: 1463
Inmate Data: Not Applicable
Cost/Impact Statement:
Incident Site: MDC Brooklyn
Incident: Electrical and Heating Outage / Civil Disturbance
Incident Date: 1/24/19 to 2/3/19
Description Cost
Emergency Generator Installation
Rental Equipment for Generators
Switch Gear Repairs
Repair of MDC Generators
Cables for Temp Generator
Restoration of Power
$138,265.17
Replace/Repair broken HVAC coils $30,125.61
HVAC System parts $57,891.12
Fire Alarm System Repairs $9,219.53
Temporary Fence $3,492.00
Overtime $330,985.46
Miller-Remick Report $437,388.55
TDY – Emergency Response Teams $388,380.00
TDY – Mechanical Services $185,690.37
TOTAL $1,581,437.81
BOP AFTER ACTION REPORT 030
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 31 of 31 PageID #: 1464
Inmate Data: Not Applicable
Cost/Impact Statement:
Incident Site: MDC Brooklyn
Incident: Electrical and Heating Outage / Civil Disturbance
Incident Date: 1/24/19 to 2/3/19
Description Cost
Emergency Generator Installation
Rental Equipment for Generators
Switch Gear Repairs
Repair of MDC Generators
Cables for Temp Generator
Restoration of Power
$138,265.17
Replace/Repair broken HVAC coils $30,125.61
HVAC System parts $57,891.12
Fire Alarm System Repairs $9,219.53
Temporary Fence $3,492.00
Overtime $330,985.46
Miller-Remick Report $437,388.55
TDY – Emergency Response Teams $388,380.00
TDY – Mechanical Services $185,690.37
TOTAL $1,581,437.81
BOP AFTER ACTION REPORT 030
Case 1:19-cv-01075-ERK-PK Document 141-1 Filed 07/01/21 Page 31 of 31 PageID #: 1464