ENERGY TRANSFER
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE.
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS.
TigerSwan
1-: . .
Solutlons tn Uncertamty
DAPL SITREP 061
- Jothorter
ENERGY TRANSFER
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE.
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS.
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS
The Highlights
North Dakota protestors rioted at AR 118 yesterday, damaging equipment with hammers and
spray paint. They also established a road block which resulted in LE arresting 30 protestors to
re-open the roadway. Iowa Fusion Center successfully located the latest M5 protest
campsite at Dolliyer Memorial State Park, which will help in tracking the protestors? future
moyements. Arrestees from yesterday?s direct action [involving protestors climbing inside a
pipe} were identi?ed as and?. Their bond
costs [$1,000 each} likely dealt a signi?cant financial blow to the group, which may impact
their execution of future direct actions.
The Details
1. EXECUTIVE SU MARY
A. North Dakota
i. Intel Update
a. Reporting on social media stated protesters are low on food and water
b. Reporting on social media also reports many protesters are contracting
pneumonia and bronchitis
ii. Past 24 Hours
a. Continued to reinforce HDD site and perimeter of the Meyer Property
b. Emplaced Hescos and wire on east side of river off Hwy 1804
c. Protesters went riot
a] Protesters damaged equipment by hitting the engine with hammers and
spray painting the equipment
d. Protesters set up a roadblock on Country Road 135 and County Road 81
a] LE arrested approximately 28 to 30 protesters and opened the roadway
e. Protesters formed up at Memorial Park in Mandan and marched to Morton
County LEC to protest
f. Protesters con ducted a march from Camp 2 to North Bridge
a] Estimated 300 to 400 protesters participated in the march
g. Protesters formed a 130+ yehicle conyoy
a] Unknown where convoy traveled to
h. Protesters set up a roadblock on Country Road 21 and Hwy 6
i. LE arrested four people at roadblock and protesters dispersed
Next 24 Hours
a. Tensions will remain high as DAPL workers continue efforts on the ROW by the
HDD site
b. Maintain static security efforts around Fortress Forward
TigerSwan Prepared for Energy Transfer Partners 1
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS
The Highlights
North Dakota protestors rioted at AR 118 yesterday, damaging equipment with hammers and
spray paint. They also established a road block which resulted in LE arresting 30 protestors to
re-open the roadway. Iowa Fusion Center successfully located the latest M5 protest
campsite at Dolliyer Memorial State Park, which will help in tracking the protestors? future
moyements. Arrestees from yesterday?s direct action [involving protestors climbing inside a
pipe} were identi?ed as and?. Their bond
costs [$1,000 each} likely dealt a signi?cant financial blow to the group, which may impact
their execution of future direct actions.
The Details
1. EXECUTIVE SU MARY
A. North Dakota
i. Intel Update
a. Reporting on social media stated protesters are low on food and water
b. Reporting on social media also reports many protesters are contracting
pneumonia and bronchitis
ii. Past 24 Hours
a. Continued to reinforce HDD site and perimeter of the Meyer Property
b. Emplaced Hescos and wire on east side of river off Hwy 1804
c. Protesters went riot
a] Protesters damaged equipment by hitting the engine with hammers and
spray painting the equipment
d. Protesters set up a roadblock on Country Road 135 and County Road 81
a] LE arrested approximately 28 to 30 protesters and opened the roadway
e. Protesters formed up at Memorial Park in Mandan and marched to Morton
County LEC to protest
f. Protesters con ducted a march from Camp 2 to North Bridge
a] Estimated 300 to 400 protesters participated in the march
g. Protesters formed a 130+ yehicle conyoy
a] Unknown where convoy traveled to
h. Protesters set up a roadblock on Country Road 21 and Hwy 6
i. LE arrested four people at roadblock and protesters dispersed
Next 24 Hours
a. Tensions will remain high as DAPL workers continue efforts on the ROW by the
HDD site
b. Maintain static security efforts around Fortress Forward
TigerSwan Prepared for Energy Transfer Partners 1
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS
Continue to reinforce HDD site {west} and perimeter of the Meyer Property
Continue to reinforce HDD site {east}
Parallel planning continues with law enforcement to secure the HDD
Bridge on Hwy 1806 north of the camps will remain closed per law enforcement
B. Iowa
i. Intel Update
a. Alex Cohen posted again with location seryices on, which pinged in Lehigh, IA
Further indicating they are camping in the area.
Protesters camp found at Dolliyer Memorial State Park
Significant because now we kn ow where the protesters are camping and may
be able to better track their moyements
b. Seyeral media outlets coyered the direct action from yesterday 10 Noy:
"Bakken Pipeline protesters go inside pipes, halt construction for seyeral
hours"
Ii}
ours
"Protesters spend hours lodged inside Dakota Access pipe?
Ii}
c. Arrestees from yesterday were:
tb} real name is?
Ic} [preyiously arrested in IL)
Id} In order to rule out they had not drilled any holes in the plastic part ofthe
pipe with the screwdriyers they had, construction had to cut away the part of
th pipe where the protesters were
All were bonded out for $1,000
Ii} Significant because this must haye drastically decreased their funds.
They did not haye $3,000 in their current legal fund, so they may haye
had to pull from their carayan fund. They will also take a significant
financial blow when they are charged for the costs associated with the
pipe that had to be cut. In addition, the group is likely short on members
that want to participate in DAs and if they keep using the same people,
they are likely to get heightened charges.
d. and haye return from ND to join MS carayan
and were at the direct action yesterday
The MS mobile carayan is growing and both female protesters are known for
trying to talk to guards
ii. Past 24 Hours
a. IA Fusion Cell positiyely identified the Mobile Direct Action camper of the
Mississippi Stand protesters in Boone County
b. 1057- 4 protesters were dropped off at Des Moines Riyer Site
TigerSwan Prepared for Energy Transfer Partners 2
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS
Continue to reinforce HDD site {west} and perimeter of the Meyer Property
Continue to reinforce HDD site {east}
Parallel planning continues with law enforcement to secure the HDD
Bridge on Hwy 1806 north of the camps will remain closed per law enforcement
B. Iowa
i. Intel Update
a. Alex Cohen posted again with location seryices on, which pinged in Lehigh, IA
Further indicating they are camping in the area.
Protesters camp found at Dolliyer Memorial State Park
Significant because now we kn ow where the protesters are camping and may
be able to better track their moyements
b. Seyeral media outlets coyered the direct action from yesterday 10 Noy:
"Bakken Pipeline protesters go inside pipes, halt construction for seyeral
hours"
Ii}
ours
"Protesters spend hours lodged inside Dakota Access pipe?
Ii}
c. Arrestees from yesterday were:
tb} real name is?
Ic} [preyiously arrested in IL)
Id} In order to rule out they had not drilled any holes in the plastic part ofthe
pipe with the screwdriyers they had, construction had to cut away the part of
th pipe where the protesters were
All were bonded out for $1,000
Ii} Significant because this must haye drastically decreased their funds.
They did not haye $3,000 in their current legal fund, so they may haye
had to pull from their carayan fund. They will also take a significant
financial blow when they are charged for the costs associated with the
pipe that had to be cut. In addition, the group is likely short on members
that want to participate in DAs and if they keep using the same people,
they are likely to get heightened charges.
d. and haye return from ND to join MS carayan
and were at the direct action yesterday
The MS mobile carayan is growing and both female protesters are known for
trying to talk to guards
ii. Past 24 Hours
a. IA Fusion Cell positiyely identified the Mobile Direct Action camper of the
Mississippi Stand protesters in Boone County
b. 1057- 4 protesters were dropped off at Des Moines Riyer Site
TigerSwan Prepared for Energy Transfer Partners 2
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS
a] Went down on Juniper
b] 4 males
c} Most likely scouting for dump site
1510- Spotted protester vehicle from yesterday, man claims to be legal analyst at
Pilot mount site. White male, driying grey/silver Subaru Outback Iowa license
plates
a] Most likely Mark Edwards
b} 1646- Road- Female asked the female guards down near DSM Riyer HDD
site where Ed [most likely Ed Fallon] was.
c} She had lots of signs in her car
Next 24 Hou rs
Secure the Des Moines Riyer HDD site during the impending pipe pull {delayed
multiple times due to drilling problems}.
b. Standby to secure the startup of the Indian Creek HDD workoyer site
C. Illinois
TigerSwan
Intel Update
a. The unusual incident that occurred at the Patoka Pump Site facility this
afternoon will be the primary focus of the security team this weekend. Efforts to
identify the unknown people and being prepared for any follow on disru ptiye
activities in the area will be ongoing
. Two UNSU BS were observed taking pictures of multiple HDD sites. They would
not identify themselves except to say they were "unaffiliated journalists?. LE
tried but they were non-responsiye about their identities. Pictures were taken of
their car plate information, hopefully linking the vehicle back to one of the two
UNSU BS is forthcoming. Plan and prep was conducted for 12 November ?Snake
Dance and Rally? in Chicago. Over 1000 people are ?going?. Multiple
organizations that are proyen to hold ANTI DAPL sentiment will be in
attendance. Link analysis has continued and links continue to be made between
BLM Chicago and anti-DAPL organizations including; all four major universities in
the area, 350.org, Veterans for peace and a myriad of others. Multiple events
are planned in the near future including 15 November ?Day of Action?. Some of
the same PDIs and organizations being linked and monitored are expected to be
present.
Past 24 Hours
a. Two UNSU BS were taking pics of multiple HDD sites in IL. Their identities are
unknown but forthcoming. An effort is being made to streamline the information
flow within "Sharefile". Plan and Prep continued for 12 November ?Snake Dance
and Rally? in Chicago. Continued to monitor the situation on the ground in
Chicago relating to non DAPL protests. Some link analysis was conducted
regarding ANTI DAPL organizations and PDIs. Suryeillance camera ops continue
Next 24 Hou rs
Prepared for Energy Transfer Partners 3
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS
a] Went down on Juniper
b] 4 males
c} Most likely scouting for dump site
1510- Spotted protester vehicle from yesterday, man claims to be legal analyst at
Pilot mount site. White male, driying grey/silver Subaru Outback Iowa license
plates
a] Most likely Mark Edwards
b} 1646- Road- Female asked the female guards down near DSM Riyer HDD
site where Ed [most likely Ed Fallon] was.
c} She had lots of signs in her car
Next 24 Hou rs
Secure the Des Moines Riyer HDD site during the impending pipe pull {delayed
multiple times due to drilling problems}.
b. Standby to secure the startup of the Indian Creek HDD workoyer site
C. Illinois
TigerSwan
Intel Update
a. The unusual incident that occurred at the Patoka Pump Site facility this
afternoon will be the primary focus of the security team this weekend. Efforts to
identify the unknown people and being prepared for any follow on disru ptiye
activities in the area will be ongoing
. Two UNSU BS were observed taking pictures of multiple HDD sites. They would
not identify themselves except to say they were "unaffiliated journalists?. LE
tried but they were non-responsiye about their identities. Pictures were taken of
their car plate information, hopefully linking the vehicle back to one of the two
UNSU BS is forthcoming. Plan and prep was conducted for 12 November ?Snake
Dance and Rally? in Chicago. Over 1000 people are ?going?. Multiple
organizations that are proyen to hold ANTI DAPL sentiment will be in
attendance. Link analysis has continued and links continue to be made between
BLM Chicago and anti-DAPL organizations including; all four major universities in
the area, 350.org, Veterans for peace and a myriad of others. Multiple events
are planned in the near future including 15 November ?Day of Action?. Some of
the same PDIs and organizations being linked and monitored are expected to be
present.
Past 24 Hours
a. Two UNSU BS were taking pics of multiple HDD sites in IL. Their identities are
unknown but forthcoming. An effort is being made to streamline the information
flow within "Sharefile". Plan and Prep continued for 12 November ?Snake Dance
and Rally? in Chicago. Continued to monitor the situation on the ground in
Chicago relating to non DAPL protests. Some link analysis was conducted
regarding ANTI DAPL organizations and PDIs. Suryeillance camera ops continue
Next 24 Hou rs
Prepared for Energy Transfer Partners 3
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS
a.
1L-"lfork the physical security package and intel development that was identi?ed by
the presence of unidentified subjects at a location in the state will be the focus.
D. South Dakota
Intel Update
a.
The Plainsman newspaper?s front-page features prominent anti-DAPL article on
Veterans Day.
a} Article featured story on how the Army Corps of Engineers wants more
cooperation from ETP.
b} Shows the media bias against the pipeline when they place a story from
North Dakota on the front page while the paper?s main story on deploying
reserye units was relegated to a lower section.
Past 24 Hours
a.
Lt Goyern or and Adjunct General were in Huron today for send-off
ceremony for the 153rd Engineer Battalion.
a] Dyer 1000 people attended the eyent.
b} PM checked all yehicles during eyent and found no anti-DAPL markers.
Two yehicles stopped and photographed the Pump Station and outlying yalye
sides today.
a] A red Dodge Carayan and a white 4-door GMC parked down the road from
the Pump Station and an unknown person climbed onto top ofthe yan to
photograph Pump Station.
Next 24 ou rs
a.
On Point personnel will continue their escort operations of electricians
throughout South Dakota.
a] On Point personnel are no longer working in two-man teams, due to
increased workload they are in single man elements.
2. TIGERSWAN NEWS UPDATE
A. Highway 5 is closed south of Mandan, and Highway 1805 near Fort Rice is
closed due to Dakota Access pipeline protest activity? KFYR-TV, By Sara
Berlinger
Lin k: ?of?Manda n?1806?near?Fort?
Ri ce osed ?du e?to? DA PL?prote st?a ct iyit y?40034892 1 .html
Summary: The Morton County Sheriff's Department says Highway 6 is closed south of
Mandan, and Highway 1306 near Fort Rice is closed due to Dakota Access pipeline
protest actiyity. The Highway re opened after 30 arrests and remoyal of debris that the
protesters were using block the highway and hinder law enforcement.
TigerSwan
Prepared for Energy Transfer Partners 4
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS
a.
1L-"lfork the physical security package and intel development that was identi?ed by
the presence of unidentified subjects at a location in the state will be the focus.
D. South Dakota
Intel Update
a.
The Plainsman newspaper?s front-page features prominent anti-DAPL article on
Veterans Day.
a} Article featured story on how the Army Corps of Engineers wants more
cooperation from ETP.
b} Shows the media bias against the pipeline when they place a story from
North Dakota on the front page while the paper?s main story on deploying
reserye units was relegated to a lower section.
Past 24 Hours
a.
Lt Goyern or and Adjunct General were in Huron today for send-off
ceremony for the 153rd Engineer Battalion.
a] Dyer 1000 people attended the eyent.
b} PM checked all yehicles during eyent and found no anti-DAPL markers.
Two yehicles stopped and photographed the Pump Station and outlying yalye
sides today.
a] A red Dodge Carayan and a white 4-door GMC parked down the road from
the Pump Station and an unknown person climbed onto top ofthe yan to
photograph Pump Station.
Next 24 ou rs
a.
On Point personnel will continue their escort operations of electricians
throughout South Dakota.
a] On Point personnel are no longer working in two-man teams, due to
increased workload they are in single man elements.
2. TIGERSWAN NEWS UPDATE
A. Highway 5 is closed south of Mandan, and Highway 1805 near Fort Rice is
closed due to Dakota Access pipeline protest activity? KFYR-TV, By Sara
Berlinger
Lin k: ?of?Manda n?1806?near?Fort?
Ri ce osed ?du e?to? DA PL?prote st?a ct iyit y?40034892 1 .html
Summary: The Morton County Sheriff's Department says Highway 6 is closed south of
Mandan, and Highway 1306 near Fort Rice is closed due to Dakota Access pipeline
protest actiyity. The Highway re opened after 30 arrests and remoyal of debris that the
protesters were using block the highway and hinder law enforcement.
TigerSwan
Prepared for Energy Transfer Partners 4
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS
Analyst Note: This is a sign of complete desperation and shows that the protesters are
past the point of reasoning with public safety of?cials. The group that carried out this
protest on Highway 1806 is likely the same rogue faction from the Red Warrior Camp
that has been at odds with the elders over the direction and public opinion of the
protest at Standing Rock. First Responders should take extra caution in the coming
weeks due to the near completion of DAPL and the unpredictable stance of the
protesters.
B. confident Dakota Access Pipeline will be completed under Trump
presidency" By CBS 12NOV15
Link: ews.comfn ew sfda kota-access-pipelin e-energy-transfer-
ce]
Summary: Kelcy Warren the CEO of the Energy Transfer Company and the driying
force of the Dakota Access Pipeline (DAPL) is Stating the he is ?100 percent? con?dent
President-elect Donald Trump will help complete the Dakota Access Pipeline
Analyst Note: In a rare and intriguing interyiew Kelcy Warren the CEO of the Energy
Transfer Company Stated that he is confident that the pipeline will be completed
under President Elect Trump. During this rare and unfiltered interyiew, Kelcy Warren
explained that the protesters haye no basis for their claims. Mr. Warren also explained
that he and his family and the workers and contractors for ETP haye receiyed threats
from Anti DAPL protestors. The Protesters haye reached a certain point of despair
following up with the unexpected presidential results. The DAPL protesters are
inherently desperate and are not looking for a peaceful solution regarding the Dakota
Access Pipeline in turn we can expect this situation to become more yolatile than
it has eyer become before.
TigerSwan Prepared for Energy Transfer Partners 5
INFORMATION CONTAINED IN THIS REPORT IS PROPRIETARY AND SENSITIVE
DO NOT RELEASE OUTSIDE OF AUTHORIZED AND APPROVED RECIPIENTS
Analyst Note: This is a sign of complete desperation and shows that the protesters are
past the point of reasoning with public safety of?cials. The group that carried out this
protest on Highway 1806 is likely the same rogue faction from the Red Warrior Camp
that has been at odds with the elders over the direction and public opinion of the
protest at Standing Rock. First Responders should take extra caution in the coming
weeks due to the near completion of DAPL and the unpredictable stance of the
protesters.
B. confident Dakota Access Pipeline will be completed under Trump
presidency" By CBS 12NOV15
Link: ews.comfn ew sfda kota-access-pipelin e-energy-transfer-
ce]
Summary: Kelcy Warren the CEO of the Energy Transfer Company and the driying
force of the Dakota Access Pipeline (DAPL) is Stating the he is ?100 percent? con?dent
President-elect Donald Trump will help complete the Dakota Access Pipeline
Analyst Note: In a rare and intriguing interyiew Kelcy Warren the CEO of the Energy
Transfer Company Stated that he is confident that the pipeline will be completed
under President Elect Trump. During this rare and unfiltered interyiew, Kelcy Warren
explained that the protesters haye no basis for their claims. Mr. Warren also explained
that he and his family and the workers and contractors for ETP haye receiyed threats
from Anti DAPL protestors. The Protesters haye reached a certain point of despair
following up with the unexpected presidential results. The DAPL protesters are
inherently desperate and are not looking for a peaceful solution regarding the Dakota
Access Pipeline in turn we can expect this situation to become more yolatile than
it has eyer become before.